SOR: Schedule of Rates

What is SOR (schedule of rates) in construction?

An SOR, or schedule of rates, is a published list of standard construction items with a description, unit and rate for each, issued by CPWD or a state public works department. Government estimates and BOQs are priced against the schedule named in the tender, and items missing from it are priced by rate analysis.

Key facts

Full form
Schedule of Rates
Central schedule
CPWD DSR (Delhi Schedule of Rates); the current civil edition is DSR 2023
Where it appears
Estimates, tender BOQs, rate justification, RA bill checks
What governs
The schedule and edition named in the tender, with its correction slips

SOR vs DSR: what is the difference?

DSR is CPWD's schedule of rates, used for central works and as a national reference. SOR is the general term, and many states publish their own schedules under names such as SOR, SSR, BSR or CSR.

Schedule nameExamples
SORUP PWD, Tamil Nadu PWD
SSR, standard schedule of ratesMaharashtra PWD, Telangana
BSR, basic schedule of ratesRajasthan PWD
CSR, common schedule of ratesPunjab, Karnataka
DSRCPWD

Each of our city BOQ pages names its state's schedule, for example Jaipur (Rajasthan PWD BSR), Bangalore, Chennai and Lucknow. Our CPWD DSR guide explains the editions and correction slips.

How do you price a BOQ from an SOR?

Match each BOQ item to a schedule item with the same description and unit, record the item number, multiply the quantity by the schedule rate, and apply any cost index the tender allows.

Worked example. CPWD DSR 2023 item 11.27 (20 mm Kota stone for skirting, risers and dado) is billed per sq m at ₹2,354.70. For 12 m² of skirting: 12 × 2,354.70 = ₹28,256.40.

Keep the schedule's unit even if you measured in running length, and check what the item description includes, such as bedding mortar or polishing, before adding separate lines for them.

What if an item is not in the SOR?

It is a non-schedule (NS) item, priced by rate analysis of materials, labour, machinery, overheads and profit, and approved before execution.

CPWD's analysis of rates (DAR) gives the accepted method; our DSR guide notes it adds 1% water charges and 15% contractor's profit and overheads. See NT item and NS item for how a non-schedule item differs from a non-tender item, and the rate analysis guide for worked analyses.

How does an SOR appear in a percentage-rate tender?

In a percentage-rate tender, the department prices the BOQ on the schedule and the bidder quotes one percentage above, below or at par with that amount. In an item-rate tender, the bidder quotes a rate against each item instead.

CPWD's GCC separates the two: CPWD-7 for percentage-rate tenders and CPWD-8 for item-rate tenders. Before you choose a percentage, check which schedule and edition the estimate uses, which item groups the percentage applies to, and how non-schedule items and provisional sums are treated. One percentage can hide expensive items, so price the whole basket first. Our tender pricing guide compares the two forms.

Which SOR applies to a project?

The one named in the tender. State-funded works usually follow the state's schedule, central works follow CPWD DSR, and the edition named in the tender governs even if a newer one exists.

Many state departments fall back on CPWD DSR for items their own schedule lacks. Private contracts can name any schedule as a reference, or none. A schedule rate is not the same as a current local quotation, so private owners often use it as a benchmark rather than a price.