Skip to main content
NT Item: Non-Tender Item

What is an NT item in construction?

An NT item, or non-tender item, is work that was not in the original tender's item list but has to be carried out under the contract. Because the tender has no rate for it, its scope, measurement basis and rate are agreed and approved separately, usually by rate analysis, before it is executed and billed.

Key facts

Full form
Non-Tender Item; related term NS item, non-schedule item
Also called
Extra item; substituted item when it replaces a tender item
Where it appears
Variation orders, extra item statements, RA bills, deviation statements
Governing document
The contract's clause on extra and substituted items

NT item vs NS item: what is the difference?

NT describes whether the item was in the tender; NS describes whether the item is in the schedule of rates. An item can be one, both or neither.

CaseNT?NS?How it is rated
Tender item with a schedule rateNoNoTendered rate
Tender item with no schedule rateNoYesTendered rate, justified by rate analysis
New work that has a schedule rateYesNoUsually from the schedule, as the contract states
New work with no schedule rateYesYesRate analysis, approved before execution

Our tender guide makes the same point: an item can be outside the chosen SOR yet listed in the tender.

How is the rate for an NT item worked out?

Follow the contract: use a similar tender rate if one exists, otherwise the schedule rate, otherwise a rate analysis of materials, labour, machinery, overheads and profit.

On CPWD-pattern contracts, a rate analysis follows the DAR structure; our DSR guide notes it adds 1% water charges and 15% contractor's profit and overheads, with material prices backed by quotations. The rate analysis guide works three complete examples.

How do you get an NT item approved and paid?

Record the instruction, agree the scope and measurement basis, submit the rate with its analysis, and get approval before you execute. Then bill it on a separate line with the approval reference.

  1. Get the written instruction: site instruction, RFI reply or a revised GFC drawing.
  2. Give the item its own number, description and unit.
  3. Submit the rate analysis with quotations.
  4. Measure it jointly on a separate sheet, with photographs.
  5. Bill it on its own line, quoting the approval.

Extra work measured first and approved later is a common reason for unpaid bills.

How should a bidder treat possible NT items at tender stage?

Ask before bidding. If drawings show work the BOQ does not list, seek a clarification instead of hiding its cost in another item's rate.

An item may be missing from the BOQ yet covered by another item's description, so read the descriptions before you call something an NT item. Our tender pricing and checking guide lists what to check, and EMD explains the deposit at risk if you change your bid later.

Common mistakes with NT items

Executing before the rate is approved, mixing NT quantities into tender items, and rating new work without evidence for the material prices.

  • No approval reference on the bill line.
  • Mixed lines. An extra buried in a tender item usually sends the whole sheet back.
  • No quotations. A rate analysis without price evidence is easy to reject.
  • Wrong label. Calling a schedule-covered item NS, or a tender item NT, invites a dispute.

Go deeper

Related terms

Sources

Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.

All construction terms in the glossary