PBG: Performance Bank Guarantee

What is a performance bank guarantee (PBG) in construction?

A PBG, or performance bank guarantee, is a bank's written promise to pay the client up to a stated sum if the contractor fails to perform the contract. The contractor arranges it after the award, within the period the contract sets, and it is returned once the obligations it secures are complete.

Key facts

Full form
Performance Bank Guarantee; contracts also say performance security or performance guarantee
How it is stated
A percentage of the contract value, set in the bid document or contract
Where it appears
Letter of acceptance, contract conditions, work order
Governing document
The contract; GFR 2017 Rule 171 for central goods procurement; CPWD GCC Clause 1 on CPWD works

How much is a performance bank guarantee?

The contract fixes it as a percentage of the contract value. GFR 2017 Rule 171, as first published, set performance security at 5% to 10% of the contract value, and CPWD's GCC 2019 uses a 5% performance guarantee under Clause 1.

Both figures are revised from time to time. GFR 2017 has been amended since 2017, and CPWD amends its GCC through circulars; our retention money guide notes a February 2026 CPWD circular on performance guarantee norms. Take the percentage from your own bid document and its corrigenda.

Worked example. On a ₹2,00,00,000 contract with a 5% performance guarantee, the PBG is 2,00,00,000 × 5 ÷ 100 = ₹10,00,000. If the same contract also deducts a 2.5% security deposit from running bills, another ₹5,00,000 is held over the life of the job.

When is a PBG submitted and released?

It is submitted after the award, within the period stated in the letter of acceptance or contract, and released after the contractor completes the obligations it covers.

GFR 2017 Rule 171 asks for the performance security to stay valid for sixty days beyond the completion of all contractual obligations, including warranty obligations. Under CPWD's GCC, the performance guarantee is returned after the completion certificate is recorded. If the contract time is extended, the guarantee usually has to be extended too, so track its expiry date against the programme.

PBG vs EMD vs security deposit

EMD secures the bid; the PBG secures performance of the awarded contract; the security deposit, or retention, is cash deducted from bills to cover defects.

A bank guarantee leaves your cash alone but uses your bank's non-fund limit and costs commission. A security deposit takes cash out of every RA bill. When a contract asks for both, a large share of the contract value can be tied up against overlapping risks, which is worth negotiating at the work order stage. See EMD for the bid-stage deposit.

When can the client invoke a PBG?

When the contractor fails to perform as the contract defines, the client can claim the guarantee from the bank up to its amount, following the contract's procedure.

Most guarantees are written as unconditional, so the bank pays on demand and any dispute about the reason is argued afterwards under the contract. That is why the guarantee wording matters: read the format attached to the bid document, check its amount, validity and claim period, and keep the bank's confirmation on file.

Common mistakes with performance guarantees

The usual mistakes are letting the guarantee lapse during an extension of time, submitting it in a format the client rejects, and forgetting to ask for its release at completion.

  • Expiry during an extension. A guarantee that lapses while work continues can be treated as a default.
  • Wrong format. Use the bid document's format word for word.
  • No release request. Commission keeps running until the bank cancels it, so apply for return as soon as the release condition is met.
  • Double security. Check whether a retention deduction and a guarantee cover the same risk.

Go deeper

Related terms

Sources

Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.