What is a letter of acceptance (LOA) in construction?
An LOA, or letter of acceptance, is the client's written notice to the successful bidder that its tender has been accepted. It states the accepted amount and starts the contract clock: the performance guarantee, the programme and the date of start are counted from it, and the formal agreement follows.
Key facts
- Full form
- Letter of Acceptance
- Issued by
- The accepting authority named in the tender
- What it starts
- Performance guarantee, programme chart, labour registrations, date of start
- Where it appears
- After tender evaluation, before the agreement and the first RA bill
What happens after the letter of acceptance?
The contractor submits the performance guarantee and the programme within the periods the contract sets, work starts on the date reckoned from the LOA, and the agreement is signed.
On CPWD works the GCC 2023 links each step to the LOA:
| Step | GCC 2023 provision |
|---|---|
| Performance guarantee | Clause 1: within the period in Schedule F from the date of issue of the LOA |
| Programme chart, labour licences, EPFO, ESIC and BOCW registration | Schedule F, Clause 1: within the days stated from the LOA |
| Date of start | Schedule F, Clause 5: the number of days after the LOA stated there |
| Signing the contract | Conditions of contract, para 9: within 15 days from the stipulated date of start |
The day counts are blank in the GCC; the NIT approving authority fills them in Schedule F for each work. Our Clause 5 guide covers the programme chart due after the LOA.
What does a letter of acceptance contain?
It identifies the work and the tender, states the accepted amount, and lists what the contractor must do next and by when. Some LOAs also record terms agreed in negotiation.
Read it for:
- the name of work, tender reference and accepted amount, matching your bid and any corrigenda;
- the time for completion and how the date of start is reckoned;
- the performance bank guarantee amount, form and deadline;
- documents to submit, such as the programme and labour registrations;
- any negotiated changes, which become part of the contract.
Your EMD stays at risk until you furnish the performance security on time.
LOA vs work order vs agreement
The LOA accepts the bid; the agreement is the signed contract document that follows; a work order instructs work, and in smaller or private jobs a work order often does all three jobs.
| Document | What it does | Typical use |
|---|---|---|
| Letter of acceptance | Accepts the tender and starts the time limits | Public and large private tenders |
| Agreement | The signed contract, bundling the tender, LOA and conditions | Signed after the LOA |
| Work order | Awards and instructs a scope at stated rates | Subcontracts and private work |
Some clients issue a letter of intent first. Read what each letter actually commits to; our work order guide lists what a work order should contain.
What should you check before acting on an LOA?
Check that the amount, scope and time match your bid, that you can furnish the guarantee in time, and that the BOQ quantities you priced still match the drawings.
The LOA is the last easy moment to raise a discrepancy. A wrong figure, a missing corrigendum or a quantity error in the tender BOQ is far harder to fix once the agreement is signed and the clock is running. A missed completion date then brings liquidated damages. Our guide to checking a tender BOQ shows where quantity errors hide.
Go deeper
Related terms
Sources
- CPWD General Conditions of Contract 2023, Clauses 1 and 5, Conditions of Contract para 9, and Schedule F
- SiteSetu: CPWD Clause 5 guide
Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.