What is EMD in construction?

EMD, or earnest money deposit, is the refundable bid security a contractor submits with a tender. It shows the bid is serious and protects the client if a bidder withdraws or changes its offer, or refuses the contract after award. Losing bidders get it back; the winner's EMD is refunded once the performance security is in place.

Key facts

Full form
Earnest Money Deposit, also called bid security
How it is stated
A fixed sum or a percentage of the estimated cost, written in the NIT
Where it appears
Notice inviting tender (NIT) and bid submission
Governing document
The NIT; for central government goods procurement, GFR 2017 Rule 170

How much is EMD in a tender?

The NIT states the exact amount, as a fixed sum or a percentage of the estimated cost put to tender. For central government procurement of goods, GFR 2017 Rule 170 says bid security should ordinarily be 2% to 5% of the estimated value.

Works departments set their own figure in their manuals and write it into each NIT, so the tender you are bidding on is the only reliable source. Read the corrigenda too: an amended estimate changes the EMD.

Worked example. Suppose an NIT puts the estimated cost at ₹1,20,00,000 and asks for EMD at 2%. The EMD is 1,20,00,000 × 2 ÷ 100 = ₹2,40,000. The 2% here is only for the arithmetic; use your NIT's figure.

How is EMD paid and when is it refunded?

GFR 2017 accepts an account payee demand draft, fixed deposit receipt, banker's cheque, bank guarantee or online payment. Unsuccessful bidders get it back after the bid validity expires, and no later than the 30th day after the award.

The bid security normally stays valid for 45 days beyond the final bid validity period (GFR 2017, Rule 170). The successful bidder's bid security is refunded on receipt of its performance security (Rule 171).

Works tenders on portals such as CPPP usually specify the payment mode and the format of any bank guarantee in the NIT. A guarantee in the wrong format, or one that expires too early, is a common reason for a bid being declared non-responsive.

When can EMD be forfeited?

EMD is at risk if you withdraw or modify your bid during its validity period, or if you win and then fail to sign the contract or to furnish the performance security on time.

That is what the deposit is for. GFR 2017 also allows a department to accept a bid securing declaration in place of a deposit: the bidder agrees that, in those same events, it will be suspended from bidding for the period the bid document states.

Read the forfeiture clause in your NIT before you upload. Some works tenders forfeit part of the EMD for a withdrawal soon after opening and all of it later; the split is in the document, not in a general rule.

EMD vs performance bank guarantee vs security deposit

EMD secures the bid, a performance bank guarantee secures the contract after award, and a security deposit is deducted from running bills to secure the quality of the work.

InstrumentStageWhat it securesReturned
EMD (bid security)With the bidThat the bidder keeps its offer and signs if it winsAfter award, or on receipt of the performance security
Performance bank guaranteeAfter awardDue performance of the contractAfter completion, as the contract states
Security deposit or retentionDeducted from RA billsQuality of work and defect rectificationAfter the defect liability period

On CPWD works, for example, the GCC 2019 runs a 5% performance guarantee under Clause 1 and a 2.5% security deposit recovered from running bills under Clause 1A. Our retention money guide compares these with private contracts.

Who is exempt from paying EMD?

Under GFR 2017 Rule 170, Micro and Small Enterprises as defined in the MSE Procurement Policy, and firms registered with the Central Purchase Organisation or the department concerned, do not submit bid security.

Exemptions in works tenders depend on the department and the NIT. If you hold Udyam registration, check whether the tender accepts it for an EMD exemption and which certificate it asks for; our contractor registration guide covers the registration side.

Go deeper

Related terms

Sources

Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.