LD: Liquidated Damages

What are liquidated damages (LD) in construction?

Liquidated damages, or LD, are a sum fixed in the contract that the contractor pays the client for finishing late, usually a rate per day, week or month of delay with an overall cap. Under Section 74 of the Indian Contract Act, the client can recover reasonable compensation up to that stated sum.

Key facts

Full form
Liquidated Damages; CPWD calls it compensation for delay
How it is stated
A rate per period of delay and a maximum, in the contract or Schedule F
Where it appears
Conditions of contract, work orders, deductions from RA and final bills
Governing law
Indian Contract Act, 1872, Section 74; on CPWD works, GCC 2023 Clause 2

How are liquidated damages calculated?

Multiply the contract's LD rate by the period of delay and the value it applies to, then stop at the cap. Each contract sets its own rate, base and cap.

CPWD works. GCC 2023 Clause 2 allows compensation for delay "with maximum rate @ 1% (one percent) maximum per month of delay to be computed on per day basis based on quantum of damage suffered", and the total "shall not exceed 10 % of the accepted Tendered Value of work". The authority named in Schedule F decides the amount.

On an accepted tendered value of ₹1,50,00,000, the cap is 1,50,00,000 × 10 ÷ 100 = ₹15,00,000. For three full months of delay, the most that can be levied is 3%, or ₹4,50,000.

Private work order. The delay clause in our work order template uses 0.5% of the order value per week of delay, capped at 10%. On a ₹20,00,000 order that is six weeks late: 6 × 0.5% = 3% = ₹60,000, against a cap of ₹2,00,000. Use your own contract's figures.

Are liquidated damages a penalty? What Section 74 means

Section 74 treats a named sum and a penalty clause alike: the client gets reasonable compensation, not more than the sum the contract names. Courts have favoured LD figures that are a genuine pre-estimate of the loss.

So the LD rate in a contract is a ceiling, not an automatic entitlement. Our work order guide cites the Supreme Court's ONGC v. Saw Pipes line on genuine pre-estimates, and recommends that the clause says so in its own words. CPWD's Clause 2 builds the same idea in: the rate is a maximum and is "based on quantum of damage suffered".

Liquidated damages vs extension of time

An extension of time moves the completion date for delays the contractor is not responsible for, so LD runs only from the extended date. Without a granted extension, LD runs from the original date.

CPWD's Clause 2 applies from the "justified extended date of completion". Under GCC 2023 Clause 5.4 the contractor must apply for an extension in writing within fourteen days of the event causing delay; our Clause 5 guide explains the hindrance register and the programme chart that support the claim. Private contracts need the same discipline: notices, a hindrance record and a revised programme.

How are liquidated damages recovered?

Usually by deduction from running or final bills, as the contract provides. On CPWD works, amounts against missed Schedule F milestones are withheld during the job and the final levy is decided under Clause 2.

Security held by the client, such as retention and a performance bank guarantee, is separate from LD and released on its own terms; our retention money guide covers those. Keep the LD calculation, the extensions granted and the delay record in the bill file, because a disputed deduction is argued from those papers.

Common mistakes with liquidated damages

The usual mistakes are signing a clause with no cap, ignoring the extension-of-time procedure, and applying the rate to the wrong base value.

  • No cap. Agree a maximum before you sign.
  • No notices. An unrecorded hindrance rarely earns an extension later.
  • Wrong base. CPWD uses the accepted tendered value; some contracts use the value of the delayed portion. Read the clause.
  • Double recovery. LD and a separate claim for the same delay loss should not both be deducted.

Go deeper

Related terms

Sources

Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.