What is a GFC drawing in construction?
A GFC drawing is a drawing stamped Good For Construction: the coordinated, issued version the site is allowed to build from. Sanction and tender drawings come before it and shop drawings after it. Only the latest GFC revision governs, and every new revision can change the quantities in the BOQ.
Key facts
- Full form
- Good For Construction; US and UK practice says IFC, issued for construction
- Who issues it
- The architect or structural consultant, through the drawing register
- Where it appears
- Site execution, BOQ preparation, RA bills and variation claims
- What governs
- The latest revision in the drawing register
GFC drawing vs tender drawing: what is the difference?
A tender drawing carries enough detail for contractors to quantify and price the work; a GFC drawing carries the coordinated dimensions, levels, finishes and notes the site builds from.
| Drawing set | Prepared for | Build from it? |
|---|---|---|
| Sanction or approval | The local authority | No |
| Tender | Contractors pricing the work | No |
| GFC | Site execution | Yes, the latest revision only |
| Shop drawing | One fabricator or vendor | Yes, for that vendor's scope, after approval |
| As-built | Owner's records | No, it is a record |
Our drawings course walks through sanction, tender, GFC and shop drawings on real sheets.
How do you check a GFC revision?
Compare the new revision with the one you priced: read the revision table, find each cloud, and list the items whose quantity or specification changed.
- Check the title block: sheet number, revision letter or number, date and the GFC stamp.
- Read the revision table for what the consultant says changed.
- Walk every revision cloud and note the BOQ items it touches.
- Re-measure only those items, and keep the old and new quantities side by side.
- Mark the superseded print so nobody on site builds from it.
Why does the GFC drawing matter for the BOQ and billing?
Quantities measured from GFC drawings are the basis for execution BOQs and bills, and the difference between the tender set and the GFC set is where most variation claims come from.
Record the sheet numbers and revisions you priced inside the BOQ or work order. When a GFC revision adds scope, that record turns an argument into a clean variation, and new work that was never in the tender becomes an NT item with its own rate. Our guide to preparing a BOQ from drawings shows how each quantity is traced to a drawing.
Common mistakes with GFC drawings
The costly mistakes are building from a superseded revision, pricing from tender drawings without recording which set you used, and treating a shop drawing approval as a change to the GFC.
- Superseded prints on site. Withdraw or stamp old revisions the day a new one arrives.
- No baseline. Without the priced sheet list, nobody can prove what changed.
- Shop drawing conflicts. Where an approved shop drawing differs from the GFC geometry, raise an RFI; the GFC governs until it is resolved.
- Quantities not re-checked. A revised lintel or plinth beam schedule changes concrete, steel and shuttering together.
Go deeper
Related terms
Sources
Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.