What is PRW in construction?
PRW stands for Piece Rate Work, and sites also use it for Piece Rate Worker. It means labour paid per unit of completed, measured work, such as per square metre of plaster or shuttering or per tonne of steel tied, instead of a daily wage. A PRW bill is the measured quantity multiplied by the agreed item rate.
Key facts
- Full form
- Piece Rate Work or Piece Rate Worker
- Paid on
- Measured quantity × agreed rate per unit
- Where it appears
- Labour work orders, measurement book, PRW or labour bills
- Key record
- Measurements signed by the site engineer and the gang leader
How is a PRW bill calculated?
Measure the work completed since the last bill, multiply by the agreed piece rate for each item, and subtract any agreed recoveries such as advances or material issued beyond the allowed wastage.
Bill on cumulative quantities, the way an RA bill does, so errors do not carry forward:
| Item: internal plaster | Quantity |
|---|---|
| Measured up to this bill | 1,240 m² |
| Measured up to the previous bill | 860 m² |
| Quantity in this bill | 380 m² |
Amount for this bill = 380 × the agreed rate per m². Measure net of openings by the same rule the work order states, so the gang and the client bill are measured alike.
Piece rate work vs daily wage labour
Daily wage pays for days present; piece rate pays for quantity completed. Piece rate links cost to output, but it needs careful measurement and quality checks.
On a daily-wage gang, the risk is slow output. On piece rate, it is quality and over-measurement: a gang paid per square metre has a reason to claim area that is not finished. Record attendance as well, because labour law records apply to both. Our measurement book guide covers how measurements are written and checked.
What should a PRW work order state?
The items, unit and rate for each, the measurement rule, who supplies which material and its allowed wastage, quality checks, and the billing and payment cycle.
- Measurement rule. For example, plaster measured net of openings as per the client contract, or another stated rule.
- Material. Free-issue material, its allowed wastage and the recovery rate for excess.
- Scope of the rate. Whether scaffolding, curing, cleaning and rework are included.
- Billing. Cumulative measurement, the retention if any, and the payment day.
Our work order format includes these clauses for labour-only and piece-rate orders.
Common mistakes in PRW billing
Paying on estimated rather than measured quantities, using a different measurement rule from the client bill, and not recovering excess free-issue material.
- No joint measurement. Measure with the gang leader and get it signed.
- Rule mismatch. If the client pays net of openings and the gang is paid gross, you lose the difference on every bill.
- Unchecked quality. Bill only work that has passed inspection.
- Units. Mixing running feet and running metres, or sq ft and m², in one bill.
The RA bill guide shows the same cumulative method on the client side.
Go deeper
Related terms
Sources
Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.