What is an RFI in construction?
In construction, RFI usually stands for Request for Information: a written question from the contractor to the architect, engineer or client to clear up a gap or conflict in the drawings, specifications or BOQ. On many Indian sites, and in CPWD's GCC 2023, RFI also means Request for Inspection of completed work.
Key facts
- Full forms
- Request for Information; also Request for Inspection
- Raised by
- The contractor's site or project engineer
- Answered by
- The architect, structural or MEP consultant, PMC or client
- Where it matters
- Drawing revisions, variations, measurement records and RA bills
Request for Information vs Request for Inspection
A request for information asks a question before the work is built; a request for inspection asks the engineer to check work that is ready, before the next activity or before measurements are accepted.
| Request for Information | Request for Inspection | |
|---|---|---|
| Purpose | Clarify drawings, specifications or scope | Get finished work or measurements checked |
| Sent to | Designer, PMC or client | Engineer-in-charge or quality engineer |
| Typical example | Slab opening shown on one drawing but not another | Reinforcement ready for a pour check |
| Outcome | A written answer, sometimes a revised drawing | Approval, or a list of corrections |
CPWD's GCC 2023 uses the second meaning: in its electronic measurement book process (Clause 6), the contractor records measurements online and "shall raise RFI(Request for Inspection) online" for the engineer to check them. Read the project's procedure to see which meaning its RFI register follows.
How do you write an RFI?
One question per RFI, with the location, the drawing numbers and revisions involved, a marked-up sketch or photo, the impact on time or cost, and the date you need the answer.
A usable request for information has:
- an RFI number, date and priority;
- the location: building, floor, grid;
- the drawing or specification references with their revisions;
- one clear question, with the conflict described;
- attachments: a marked-up drawing, sketch or photo;
- the impact if unanswered, and the answer-by date.
Our RFI guide has examples from Indian sites, such as a slab opening shown on the architectural drawing but missing from the structural one.
When does an RFI become a variation?
When the answer changes the scope, specification, quantity or time, it is no longer just a clarification: record it as a variation or a new item.
An answer that issues a revised GFC drawing can change quantities across many items. Work that was never in the tender becomes an NT item with its own rate. Raise the commercial point when the answer arrives, not at the final bill.
How do RFIs affect measurement and billing?
They are evidence. The RFI number on a measurement line shows why a quantity changed or why extra work was done, which is what a certifying engineer looks for.
Our JMS guide recommends citing the site instruction, RFI or variation order number and date on every extra line. Keep RFIs in one register, and link each answer to the drawing revision it produced. When a BOQ is prepared from drawings, open RFIs are also the list of assumptions to state; our guide to preparing a BOQ from drawings shows how.
Common mistakes with RFIs
The usual mistakes are several questions in one RFI, no drawing revision quoted, verbal answers never written down, and building on an assumption while the RFI is open.
- Bundled questions. One answer gets lost; split them.
- No revision. "As per drawing" means nothing without a revision letter.
- Verbal answers. Write the instruction into the RFI response.
- Raised too late. Ask before the pour, not the night before.
Go deeper
- RFI format and workflow for Indian sites
- How to prepare a BOQ from drawings
- JMS format and extra items
Related terms
Sources
- CPWD General Conditions of Contract 2023, Clause 6 (RFI, Request for Inspection, in the EMB process)
- SiteSetu: RFI guide
- SiteSetu: JMS guide (RFI references on extra lines)
Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.