What is DPC in construction?
DPC stands for damp proof course: a continuous layer of damp-resisting material laid across the full width of the walls at plinth level. It stops moisture in the ground from rising through the masonry into the walls above. CPWD's schedule item for it is a 40 mm layer of cement concrete 1:2:4, measured in square metres.
Key facts
- Full form
- Damp Proof Course
- Where
- On top of the plinth masonry, under the walls of the superstructure
- Common specification
- CPWD item 4.10: 40 mm cement concrete 1:2:4 with 12.5 mm aggregate; the drawing may specify another material
- Unit
- m², stating thickness (IS 1200 Part 3, clause 19)
What is the use of DPC?
DPC breaks the path of moisture from the ground into the walls. Without it, damp climbs the masonry and shows up as peeling paint, damp patches and white salt deposits above the skirting.
Brick and mortar draw water upwards. A dense, continuous layer across the wall at plinth level cuts that path. Our substructure take-off lesson describes the damage it prevents and how to measure it.
DPC is one part of damp-proofing a building, not all of it. IS 3067 covers the general design details for damp-proofing and waterproofing; our waterproofing guide summarises the related standards.
What is the thickness and mix of DPC?
The drawing or specification sets it. CPWD's item 4.10 is damp-proof course 40 mm thick in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate of 12.5 mm nominal size).
CPWD's item 4.13 adds a coat of VG-10 bitumen at 1.7 kg per square metre on the damp-proof course, where the specification asks for it. Specifications also add an integral waterproofing compound as an extra item, dosed as the manufacturer's datasheet says. Other materials, such as bitumen membranes, are used where the drawing calls for them.
If your drawing simply says "DPC", ask for the material and thickness in writing before you price it. A 40 mm concrete layer and a membrane are different items with different rates.
Where is DPC laid?
At plinth level, across the full width of every wall that rises from the ground, above the finished external ground level, and continuous at corners and junctions.
The DPC sits on the levelled top of the plinth masonry, below the first course of the superstructure walls. It must run without gaps where walls meet; a break at a junction lets damp through. The structural or architectural drawing gives its level; it should stay above the external ground and plinth protection, or water simply bypasses it.
Vertical damp-proofing, such as on a basement wall, is a different item and is measured separately.
How is DPC measured in a BOQ?
IS 1200 Part 3 measures DPC in square metres, stating its thickness: the length of wall it covers times the width of the wall, with vertical and horizontal courses kept as separate items.
The item includes levelling up and preparing the brickwork to receive the DPC, and any formwork it needs (clause 19.1).
Worked example. A ground floor is 12.00 m × 9.00 m to the outside, with 230 mm walls and two internal cross walls of 230 mm. Whether the DPC runs across door openings is the drawing's call; here it runs through.
| Wall | Working | Area |
|---|---|---|
| External, centre-line length 41.08 m | 41.08 × 0.23 | 9.4484 m² |
| Two internal walls, 8.54 m each | 2 × 8.54 × 0.23 | 3.9284 m² |
| DPC, 40 mm thick | 13.38 m² |
For materials, 13.3768 m² × 0.04 m is 0.535 m³ of concrete; the concrete calculator splits that into cement, sand and aggregate.
Is DPC needed if there is a plinth beam?
Follow the drawing. A plinth beam is a structural member and DPC is a damp barrier; some designs treat a dense plinth beam as the barrier and others still specify a DPC over it.
A plinth beam ties the columns at plinth level and carries the ground-floor walls. Whether the walls above also need a separate damp-proof course is a specification decision. Ask the designer if the drawings are silent, and price exactly what the answer says.
Common mistakes with DPC
The usual mistakes are breaks at corners and junctions, a DPC below the outside ground level, skipping the bitumen coat or curing, and dropping the item from the estimate.
- Gaps at junctions. Damp finds the one place the layer stops.
- Laid too low. If the outside ground or paving ends up higher than the DPC, it no longer works.
- Not cured. A concrete DPC is concrete; cure it like any other.
- Missing from the BOQ. Some estimates leave out the damp-proof course and plinth work; read the exclusions.
Go deeper
- Anti-termite treatment and DPC take-off (free lesson)
- Concrete calculator
- Waterproofing cost per sq ft
Related terms
Sources
- TCIL tender estimate on DSR 2023, quoting CPWD items 4.10 (40 mm DPC in CC 1:2:4) and 4.13 (VG-10 bitumen coat at 1.7 kg per m²)
- IS 1200 Part 3:1976, clause 19, damp-proof courses (BIS)
- SiteSetu Academy: anti-termite treatment and DPC lesson
- SiteSetu: waterproofing guide (IS 3067 and related standards)
Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.