What is curing of concrete in construction?
Curing is keeping freshly placed concrete moist, at a suitable temperature, while the cement hydrates and the concrete gains strength. IS 456 asks for exposed surfaces to be kept wet for at least 7 days with ordinary Portland cement, and at least 10 days where mineral admixtures or blended cements are used.
Key facts
- Standard
- IS 456:2000, clause 13.5
- Minimum moist curing
- 7 days with OPC; 10 days with mineral admixtures or blended cements; 10 days in dry and hot weather
- Methods
- Ponding or wet coverings (13.5.1); curing compounds or sheeting (13.5.2)
- In a BOQ
- Part of the concrete item, not a separate line, in schedules such as CPWD DSR
What is the curing period of concrete?
Under IS 456 clause 13.5.1, at least 7 days from placing for ordinary Portland cement, at least 10 days where mineral admixtures or blended cements are used, and not less than 10 days in dry and hot weather.
| Concrete | Minimum moist curing (IS 456, 13.5.1) |
|---|---|
| Ordinary Portland cement (OPC) | At least 7 days from the date of placing |
| With mineral admixtures or blended cements, such as PPC | At least 10 days |
| Exposed to dry and hot weather | Not less than 10 days |
| With mineral admixtures or blended cements | The clause recommends extending the minimum periods to 14 days |
Much site concrete in India uses PPC or slag cement, so the 10-day figure is the one many sites should plan for. These are minimums; a specification can ask for more.
What are the methods of curing concrete?
Moist curing, by ponding or by keeping wet sacking, canvas or hessian on the surface, and membrane curing, using an approved curing compound or polyethylene sheeting.
IS 456 clause 13.5.1 describes moist curing: exposed surfaces kept continuously damp or wet by ponding, or covered with sacking, canvas, hessian or similar material kept constantly wet. Clause 13.5.2 allows approved curing compounds in place of moist curing, with the engineer-in-charge's permission, applied to all exposed surfaces as soon as possible after the concrete has set. Close-fitting polyethylene sheeting may also be used as a barrier against evaporation.
| Element | Usual method |
|---|---|
| Slabs and floors | Ponding with small bunds, or wet hessian |
| Columns and walls | Wet hessian wrapped and kept wet, or a curing compound |
| Large or high surfaces | Curing compound, where approved |
Why is curing important?
Cement needs water to hydrate. Concrete that dries out early stops gaining strength near the surface, shrinks and cracks, and becomes more permeable, which lets water reach the steel.
IS 456 clause 13.5 says preventing moisture loss matters most when the water-cement ratio is low, when the cement gains strength fast, and when the concrete contains slag or fly ash. It also asks for the curing regime to prevent high temperature gradients. Poor curing shows up as dusty surfaces, plastic shrinkage cracks and weak cover concrete, and it can make cube results misleading if the cubes are cured better than the structure.
Is curing a separate item in the BOQ?
Usually not. Schedules such as CPWD DSR include curing in the concrete item, so it is the contractor's obligation within the concrete rate, and it is checked through site records.
Our RCC rate guide notes that CPWD DSR 2023 item 5.33 includes pumping and curing. Because nobody bills for it separately, curing is the step most often cut short. Keep a curing register by pour and date, and check it alongside cube results. For quantities, the concrete calculator works out the cement, sand and aggregate for a pour.
Common mistakes in curing
The usual mistakes are stopping after three or four days, curing only the top of slabs and not the sides of beams and columns, letting surfaces dry between waterings, and using OPC periods for PPC concrete.
- Too short. Seven days is the OPC minimum; blended cements need at least ten.
- Intermittent wetting. IS 456 asks for surfaces kept continuously damp; a morning splash is not curing.
- Vertical faces forgotten. Columns and beam sides dry fastest.
- Late start. Protect the surface as soon as it can take it; a curing compound goes on as soon as possible after the concrete has set.
Poorly cured concrete is also harder to repair; see honeycombing for how defects are handled.
Go deeper
- RCC work rate: what the concrete item includes
- Concrete calculator
- PCC in building construction (curing of blinding concrete)
Related terms
Sources
- IS 456:2000, clauses 13.5, 13.5.1 and 13.5.2 (BIS)
- SiteSetu: RCC work rate guide (DSR 2023 item 5.33 includes curing)
Checked 2026-11-03. Contract documents, tender conditions and the structural drawings for your project take precedence over the general rules on this page.