Skip to main content

Worked Example: One Full Floor Takeoff

Lesson 19 of 60 · 7 min read

This is the lesson the module was building toward: the complete takeoff of the course floor on one page. Nothing new is introduced — every rule was earned in Lessons 1–7 — but assembly is its own skill: keeping conventions consistent, catching what earlier sheets missed, and finishing with totals a contractor, a bank valuer or a RERA project engineer can audit line by line. Work through it with a calculator; every number should reproduce.

The floor (from Lesson 1): 12 columns 230 × 380 on a 3.0 m grid, beams 230 × 450 on all lines, slab 125 mm at 9.38 × 6.23 m, floor height 3.0 m, M25 + Fe 500. Walls: external 230 mm brick in all perimeter bays with 6 windows 1.2 × 1.2 and one door 1.0 × 2.1; internal 115 mm partitions 12.0 m run with two 0.9 × 2.1 doors. Finishes: 12 mm internal, 6 mm ceiling, 18 mm external plaster; putty + primer + 2-coat emulsion inside.

Step 1 — Concrete (Lesson 1)

Lesson data table
MemberCalculation
Columns (12)0.23 × 0.38 × 2.55 × 122.67
X-beams28.14 m × 0.23 × 0.3252.10
Y-beams22.16 m × 0.23 × 0.3251.66
Slab58.44 m² × 0.1257.30
Total M2513.73

Step 2 — Shuttering (Lesson 2)

Lesson data table
ItemCalculation
Columns1.22 × 2.55 × 1237.33
Beams0.88 × 50.3044.26
Slab soffit58.44 − 11.5746.87
Slab edges31.22 × 0.1253.90
Total132.36 (= 1,425 sqft)

Step 3 — Steel (Lessons 4–5)

Slab: 417.2 kg (Lesson 5). Beams: each X-line 104.35 kg × 3 = 313.1 kg. Each Y-line (6.23 m, 2 spans of 2.77): bottom 3–16 at CL 6.516 = 30.9 kg; top 2–12 at CL 6.532 = 11.6 kg; extra top 2–16 × 2.18 at one interior support = 6.9 kg; stirrups 20 per span × 2 = 40 × 1.224 × 0.395 = 19.3 kg → 68.7 kg × 4 lines = 274.9 kg. Beams total 588.0 kg.

Columns: per column 4–16 verticals × 3.80 m (3.0 floor + 0.80 lap at 50d, per drawing) = 24.0 kg, plus 21 ties (8 mm, CL 964 mm for 40 cover) = 8.0 kg → 32.0 kg × 12 = 384.2 kg.

Lesson data table
Componentkg
Slab417.2
Beams (7 lines)588.0
Columns (12)384.2
Fixed steel1,389
+ 3% cutting wastage + binding wire (~10 kg/t)≈ 56
Order quantity≈ 1,445 kg

Step 4 — Masonry (Lesson 3)

External 230 walls run clear between columns: X bays 2 × 3 × 2.62 = 15.72 m; Y bays 2 × 2 × 2.77 = 11.08 m; total 26.80 m × 2.55 high × 0.23:

  • Gross 15.72 m³ − 6 windows (6 × 1.44 × 0.23 = 1.99) − door (2.1 × 0.23 = 0.48) = 13.25 m³
  • Bricks: 13.25 × 500 = 6,625 + 5% → order ≈ 7,000; cement 13.25 × 1.25 ≈ 16.6 bags; sand 13.25 × 0.26 ≈ 3.45 m³

Internal 115 partitions (m² item): 12.0 × 2.55 = 30.6 − 2 doors (3.78) = 26.82 m² (= 3.08 m³; ≈ 1,540 bricks + 5% → ≈ 1,620; cement ≈ 3.9 bags; sand ≈ 0.80 m³).

Step 5 — Plaster and paint (Lessons 6–7)

  • Internal wall plaster 12 mm: inner faces of external walls 29.08 m perimeter × 2.875 = 83.6 − openings one-face (6 × 1.44 + 2.1 = 10.74) = 72.9 m². Partitions both faces 2 × 12.0 × 2.875 = 69.0 − doors one-face 3.78 = 65.2 m². Total 138.1 m².
  • Ceiling plaster 6 mm: slab soffit 46.87 + beam soffits 11.57 + room-side beam faces ≈ 23.0 = ≈ 81.4 m² (beam ribs make the ceiling bigger than the plan — the most-missed area in finishing bills).
  • External plaster 18 mm: 31.22 m × 3.0 = 93.7 m² (openings' single-face deductions were taken inside; reveals here are smaller on the inner side).
  • Putty/primer/emulsion (internal): 138.1 + 81.4 = 219.5 m² → putty ≈ 165 kg, primer ≈ 22 L, emulsion 2 coats ≈ 31 L.
One floor, all quantities. The course floor closed out: 13.73 m³ concrete, 132.4 m² shuttering, 1,389 kg steel, 13.25 m³ + 26.8 m² masonry, 313 m² plaster, 219.5 m² paint system.

The summary table

Lesson data table
#ItemUnitQty
1M25 concrete — columns2.67
2M25 concrete — beams3.76
3M25 concrete — slab7.30
4Shuttering (all members)132.36
5Fe 500 steel (fixed, per BBS)kg1,389
6Brickwork 230, in CM 1:613.25
7Brickwork 115 partition26.82
8Internal plaster 12 mm138.1
9Ceiling plaster 6 mm81.4
10External plaster 18 mm93.7
11Putty + primer + emulsion219.5

Indicative material cost only (mid-2026 ranges from earlier lessons — always price from current local quotations; labour and contractor margins come in Module 4): RMC ≈ Rs. 75,000–1,03,000; steel ≈ Rs. 75,000–92,000; bricks (≈ 8,620) ≈ Rs. 70,000–1,03,000 metro red-clay (AAC often cheaper per m³); mortar + plaster cement ≈ 45 bags ≈ Rs. 17,000–19,000; sand ≈ 3.3 brass ≈ Rs. 12,000–20,000; paint system ≈ Rs. 15,000–22,000. Order of magnitude: Rs. 2.7–3.6 lakh of material for one structural floor with envelope and internal finishes — which is why a one-page takeoff, not a thumb rule, should authorise these purchases.

Sanity ratios: the QS's smell test

  • Steel density: 1,389 ÷ 13.73 = 101 kg/m³ — typical residential frames run 90–110. Below 80, recheck the BBS; above 130, recheck the drawing (or the biller).
  • Shuttering ratio: 132.36 ÷ 13.73 = 9.6 m²/m³ — inside the 8–12 band from Lesson 2.
  • Concrete intensity: 13.73 m³ ÷ 629 sqft plan = 0.022 m³/sqft — the common residential band is roughly 0.02–0.025 m³ per sqft of slab area.
  • Slab steel: 7.1 kg/m² — light but plausible for 3 m two-way panels; longer spans climb fast.

Thumb rules never replace a takeoff — but a takeoff that violates all its thumb ratios is telling you to find the error before the money moves.

How this sheet protects you

Every RA bill from the thekedar — RCC per sqft, masonry per m³, plaster per sqft — now gets checked against one authoritative page instead of being renegotiated from zero. Attach the pre-pour joint measurements, brick truck counts, weighbridge slips and BBS marks behind it, and you have the documentation stack that decides disputes in the RERA era: not the loudest voice, the best paper. For a self-builder, this sheet is also the defence against the oldest line in construction — "itna toh lagta hi hai, sahab" (that much is simply needed) — because now you know, to the bag and the bar, how much actually is.

Common mistakes at assembly

  • Switching conventions midway — e.g., columns to beam soffit in concrete but full height in shuttering. One convention, whole sheet.
  • Scope holes: this takeoff deliberately excludes the staircase, parapet, lintels/chajjas, and lift/plumbing shafts — list exclusions explicitly so nobody assumes they are inside.
  • Copying quantities between floors without checking column reductions, wall layout changes or balcony additions.
  • No wastage line: fixed ≠ ordered. Steel +3–5%, bricks +5%, and cement rounded to full bags.

Where the module leaves you

You can now measure everything that makes a floor. What you cannot yet do is price it like a professional — material constants, labour coefficients, and contractor rates per item. That is Module 4: rate analysis and building the BOQ, where these eleven quantities meet their rupee rates.

Key takeaways

  • One floor closed out: 13.73 m³ concrete, 132.4 m² shuttering, 1,389 kg steel, 13.25 m³ + 26.8 m² masonry, 313 m² plaster, 219.5 m² paint.
  • Assembly discipline: one convention throughout, exclusions listed explicitly, wastage lines separating fixed from ordered quantities.
  • Sanity ratios catch errors: ~101 kg steel/m³ (band 90–110), 9.6 m² shutter/m³ (band 8–12), ~0.022 m³ concrete per sqft of plan.
  • The ceiling plaster area (81.4 m²) exceeds beam-strip-netted soffit area because beam ribs add surface — the most-missed finishing quantity.
  • Roughly Rs. 2.7–3.6 lakh of material rides on this one page at indicative mid-2026 rates — takeoffs authorise purchases, thumb rules do not.
  • The takeoff plus its evidence trail (joint measurements, challans, BBS marks) is what wins billing disputes in the RERA era.

Verify on site

  • Rebuild this floor's takeoff for your own current project before starting Module 4.
  • File pre-pour joint measurement sheets, RMC challans and weighbridge slips behind the takeoff page.
  • List excluded items (stairs, parapet, lintels, shafts) at the bottom of every takeoff sheet.
  • Run the three sanity ratios on every floor you measure and investigate outliers before billing.
  • Compare each thekedar RA bill line against the takeoff item it draws from.
  • Re-verify quantities on the first repetition floor instead of copying — layouts drift.

Check your understanding

5 questions. Answering them marks this lesson complete — results stay on your device.

  1. 1. Total concrete for the course floor (columns 2.67, beams 3.76, slab 7.30)?
  2. 2. The floor shows 1,389 kg of steel in 13.73 m³ of concrete. Verdict?
  3. 3. External brickwork: 26.80 m × 2.55 m × 0.23 m gross, with 6 windows of 1.44 m² and one 2.1 m² door. Net volume?
  4. 4. Why is the ceiling plaster area (81.4 m²) larger than the netted slab soffit (46.9 m²)?
  5. 5. Which of these is deliberately NOT inside this floor takeoff and must be listed as an exclusion?

Want the free certificate?

The whole course is free and open — no signup needed to learn. Enter your details only if you want us to track your progress on this device and issue a named certificate after the final assessment.