Estimation13 min read

BOQ for Interior Works: Format, 2BHK Sample and Excel

A measured compact 2BHK interior BOQ with room arithmetic, joinery and fixture schedules, blank vendor rates and a downloadable Excel template.

Y

Civil Engineer | IIT Bombay | ex-IOCL

By Yogesh Dhaker • Published

An interior BOQ lists each fit-out item with its location, specification, measurement unit, quantity, rate and amount. It covers ceilings, joinery, finishes, furniture and services, using measured areas, running lengths and counts so vendors can price the same scope.

Download the interior BOQ format in Excel. It includes a fictional 2BHK measurement sheet, 26 BOQ lines and a trade abstract. Rates and amounts start blank. The quantities below are an example dated 25 October 2026, not a quotation or a measurement of your home.

How an interior BOQ differs from a civil BOQ#

A civil BOQ commonly separates excavation, concrete, masonry and reinforcement. An interior fit-out BOQ needs more detail about visible finishes, cabinet construction, fittings and installation. The flat's floor area alone cannot describe those items.

A wardrobe may be quoted per sq ft of front area, while a kitchen carcass may be quoted per running ft at a stated depth and height. A shutter can be measured by its face area, a countertop by plan area, and a light fitting by number. If a supplier prices carcass board area instead, require a cutting/component schedule: that area is different from the cabinet's front area. State the basis beside every quantity.

Use one unit system for each item. One foot is exactly 0.3048 m, so one sq ft is 0.09290304 m². Do not apply a per-running-ft rate to a running-m quantity. The worked download uses metres, m² and counts.

BOQ format for interior work: the columns to keep#

Article table: Column What to record Trade and item code Ceiling C01,
ColumnWhat to record
Trade and item codeCeiling C01, kitchen K01, wardrobe R01
Location / measurement referenceRoom, elevation, drawing number and revision
Specification and inclusionsMaterial, thickness, finish, brand/model where selected, fixing and installation
Unit and measurement basism² of front area, running m at defined section, nos or a defined set
QuantityLinked to a measurement sheet, not entered as a budget allowance
RateVendor's rate per exactly the stated unit
AmountQuantity × rate, rounded to two decimals
ClarificationsUnselected materials, exclusions, alternatives and provisional scope

Keep the drawing revision and vendor clarification record with the saved workbook. The example has descriptions to complete before pricing: “board specification to confirm” is an unresolved choice, not a procurement instruction.

Trade sections: what each line must specify#

These are recommended quote fields. Units and inclusions must be agreed with the vendor; the table is not a universal schedule of rates.

Article table: Trade Measurement unit / basis Specify before requesting a rate
TradeMeasurement unit / basisSpecify before requesting a rate
False ceilingm² of board/grid ceiling; separate cove lengths and access panelsGypsum board or grid/tile type, thickness, frame sections/spacing, suspension, level, joint treatment and paint inclusion
Wall panellingm² of specified faceSubstrate/backing, board grade/thickness, laminate/veneer, edge banding, grooves and fixing
Modular kitchen carcassRunning ft or m at stated depth and height, or explicitly defined board areaBase and wall units separately; board grade, thickness, back panels, shelves, legs, internal finish and installation
Kitchen shuttersSq ft or m² of shutter faceBoard, finish on each face, edge banding thickness, handle profile and fitting
CountertopSq ft or m² of agreed plan area, or running length at fixed widthStone/type, thickness, edge profile, joints, backsplash, sink/hob cut-outs and installation
Kitchen hardwareNos, pairs or a defined setBrand and series, hinge quantity, soft-close mechanism, runner length/load, baskets and handles
WardrobesSq ft or m² of front elevation, or running ft at a stated height/depthCarcass, shutters, backs, shelves, loft inclusion and finish; separate internal fitting schedule
Loose furnitureNosDimensions, frame/board, upholstery, finish, delivery, assembly and mattress/cushion exclusions
Flooring and skirtingm² laid area; running m of skirting at stated heightProduct/size, substrate preparation, adhesive/bedding, grout, edge work and areas behind fixed furniture
Painting and polishm² of the specified surface and coating systemPreparation, primer, coat count, product, substrate and repairs; polish for exposed veneer separately
Electrical points and lightsNos of each point/fixture type; metres for separately measured routesWire size/brand, conduit, point definition and length allowance, switchgear, fixture model, driver and testing
Plumbing fixturesNos of each fixture or defined setBrand/model, taps, wastes, traps, connections and installation; new pipe routes measured separately
Glass and partitionsm² at defined height; doors separatelyGlass type/thickness, framing, channels, fittings, seals and edge treatment
Doors and hardwareNos of specified door sets; nos/sets of fittingsOpening size, frame, shutter, finish, hinges, lock/handle, stopper and fixing
Site protection and debris removalm² protected surface; defined job or trips for removalProtection material/layers, lift/common-area protection, loading, transport and disposal scope

False ceiling deductions need their own rule#

The accessible IS 1200 Part 10:1973, clauses 3.1–3.4, measures flat ceiling/lining work in m², describes material, thickness and fixing, and treats supporting members separately unless specified otherwise. Clause 3.4 makes no deduction for each opening up to 0.4 m²; larger openings are deducted in full and their formation labour is measured separately. Check the edition and composite-item wording adopted by your contract. Source: BIS standard, including the February 1989 amendment.

For example, a 0.6 × 0.6 m opening is 0.36 m², while a 0.8 × 0.8 m opening is 0.64 m². Under that cited rule, the second opening is deducted. An access-panel supply item is a separate scope question. The workbook leaves deductions as reviewed inputs; it does not decide the contract rule for you.

The sample ceiling item expressly includes frame, fixing and joint treatment, with paint separate. No opening exceeds 0.4 m² in its assumed layout. Use the false ceiling cost and scope guide when choosing the system and comparing inclusions.

Sample BOQ for interior works: a measured compact 2BHK#

This fictional flat has the following clear internal room dimensions, all in metres. The 67.25 m² total excludes wall thicknesses, balcony and common areas. It is not a saleable-area claim. All rooms are 3 m high. Only the hall and two bedrooms receive a new flat false ceiling.

Article table: Room Length × width Floor area m² New false ceiling
RoomLength × widthFloor area m²New false ceiling m²
Hall5 × 420.0020.00
Bedroom 14 × 3.514.0014.00
Bedroom 23.5 × 3.512.2512.25
Kitchen3 × 39.00—
Passage3 × 26.00—
Bathroom 12 × 1.53.00—
Bathroom 22 × 1.53.00—
Total20 + 14 + 12.25 + 9 + 6 + 3 + 367.2546.25

The floor finish extends under cabinetry in this example. Different dry-room and wet-room finishes must be split into separate rows before pricing. No purchase wastage is added to the measured floor area.

Joinery assumptions are a straight 3.6 m base kitchen run, a 2.4 m wall-unit run and one 1.8 m wide × 2.1 m high wardrobe in each bedroom. There are no kitchen corner overlaps, appliance gaps or wardrobe lofts. Base units are 0.6 m deep × 0.75 m high; wall units are 0.35 m deep × 0.7 m high. Wardrobes are 0.6 m deep.

Measured quantities, with rates left for the vendor#

Empty rate and amount cells are intentional. There is no total cost until the specifications are settled and every required rate is entered.

Article table: Item Quantity calculation Unit Quantity Rate ₹/unit Amount ₹ Gypsum
ItemQuantity calculationUnitQuantityRate ₹/unitAmount ₹
Gypsum ceiling including agreed frame/joints20 + 14 + 12.25m²46.25
Hall wall panel, one face3 × 2.4m²7.20
Base kitchen carcass only1 × 3.6running m3.60
Wall kitchen carcass only1 × 2.4running m2.40
Base shutter fronts3.6 × 0.75m²2.70
Wall shutter fronts2.4 × 0.7m²1.68
Countertop, agreed gross plan area3.6 × 0.6m²2.16
Kitchen hardware package1 defined packageset1
Wardrobes, front area including carcass/shutters2 × 1.8 × 2.1m² front7.56
Wardrobe internal fitting packages1 per wardrobe × 2set2
Beds1 per bedroom × 2nos2
Hall sofa1nos1
Flooring, room-wise split requiredSum of seven floor areas abovem²67.25
Bedroom skirting only2 × (4 + 3.5) + 2 × (3.5 + 3.5) − 2 × 0.9 − 2 × 1.8running m23.60
Selected ceiling primer + emulsion systemSame 46.25 m², measured oncem²46.25
Light wiring points6 + 3 + 3 + 2 + 2 + 1 + 1nos18
Socket points4 + 3 + 3 + 2nos12
Light fixtures1 at each of 18 light pointsnos18
Replacement basins1 per bathroom × 2nos2
Kitchen sink1nos1
Replacement WC sets1 per bathroom × 2nos2
Fixed glass partition, no opening2 × 2.4m²4.80
Bedroom door sets2 openings, each 0.9 × 2.1 mnos2
Door hardware packages1 per new door × 2set2
One layer of floor protectionSame seven-room aream²67.25
Debris removalDefined provisional scope, not a dimension-based quantityjob1

The kitchen hardware package assumes 20 hinges, 10 handles and three pairs of drawer runners. Each wardrobe package assumes nine hinges, three handles, one hanging rail and one pair of runners. Each door package contains three hinges, one lock/handle set and one stopper. These are example schedules, not fittings inferred from floor area; revise them against approved elevations and hardware selections.

The countertop uses an expressly agreed gross plan-area basis, with one sink cut-out and edge finishing included in that rate. If your vendor deducts the cut-out and prices its labour separately, revise both lines together. Bedroom skirting omits two 0.9 m door openings and the two 1.8 m wardrobe backs; no returns are included.

The electrical count is an assumed point schedule: hall, bedrooms, kitchen, passage and bathrooms in that order for the light points. Socket counts cover hall, bedrooms and kitchen. Confirm circuits, point routes and appliance loads before pricing. Fixture models and wet-area requirements need separate specification rows where they differ.

Wall repainting, exposed-wood polish, new plumbing routes, distribution-board changes, appliances and demolition are excluded from this particular sample. Add them when required. For wall-opening deductions and separate preparation/coating lines, use the painting BOQ format and measured example.

How to use the interior fit-out BOQ format in Excel#

The download has three linked sheets:

Article table: Sheet Editable inputs Calculated results Abstract None; it reads the
SheetEditable inputsCalculated results
AbstractNone; it reads the BOQTrade item counts, rates entered and complete trade amounts
BOQSpecifications and vendor ratesMeasurement-linked quantities and quantity × rate amounts
MeasurementsRoom dimensions, joinery dimensions, reviewed deductions and scheduled countsRoom areas, perimeters and item quantities
  1. Save a project copy and record the drawing revision with it.
  2. Replace room and joinery measurements. Amber cells are inputs; linked dimensions and quantities remain formulas.
  3. Check deductions and scope, including floors below cabinets and skirting behind wardrobes.
  4. Replace the assumed fixture and hardware schedules. Confirm all brand, model, thickness and finish choices.
  5. Split rows with different specifications, especially flooring and light fixtures. Extend the BOQ formulas, trade ranges and abstract references when adding rows; this is a fixed example, not an automatic drawing reader.
  6. Enter each vendor's rates in a separate copy of the same agreed BOQ. Use zero only when that item is deliberately included at no additional price.
  7. Recalculate in Excel and trace a ceiling, cabinet and counted item through to its amount. A blank rate leaves its amount blank. A trade total remains blank until every rate in that trade is entered.

Negative rates and invalid required dimensions produce an error. The workbook requests recalculation on opening. It has no macros and supplies no market rates.

Compare two interior quotes line by line#

Start with the same item codes, quantities and units. Then compare specifications and inclusions before comparing totals. A lower sum can simply omit a countertop or use a thinner back panel.

Article table: Check What to resolve in both quotes Carcass and shutters
CheckWhat to resolve in both quotes
Carcass and shuttersSame board grade/thickness, inner and outer finish, shelf count and measurement basis
Edge banding and backsThickness, exposed-edge treatment and back-panel material included in writing
HardwareSame brand, series, number of hinges/runners, load rating and fitting charge
CountertopSame material, thickness, width, edge, backsplash and cut-out treatment
InstallationWho supplies fasteners, supports, sealants, fitting labour and final adjustments
Transport and accessDelivery, unloading, floor-level carrying, lift protection and working-hour constraints
Surface preparationRepairs, levelling, joint work and primer included once
ServicesPoint wiring versus fixture supply; existing connections versus new pipe/cable routes
Commercial termsVendor's separate GST disclosure, payment stages, validity and warranty wording

Keep unresolved items in a clarification list. Ask the vendor to reissue the quote after settling them. Do not insert an assumed tax percentage or treat an omitted price as zero. If one vendor offers a composite wardrobe rate including fittings, remove the separate fittings charge for that comparison or obtain a matching split from both vendors.

For reported budget bands and material/hardware choices, see interior design cost per sq ft in India. Those broad budget bands serve a different purpose from a measured item-rate quote.

For your project, get a BOQ from your drawings. Send layouts, elevations, ceiling plans and the finish/fixture schedule so the desk can measure the work and list missing specifications.

Frequently asked questions#

What should a BOQ for interior work include?#

Trade and item codes, locations, specifications, measurement units, quantities, rates and amounts, backed by room and joinery measurements. Include installation and ancillary work explicitly, and record unresolved selections before comparing vendors.

Is there an interior BOQ format in Excel to download?#

Yes. Download the prebuilt interior BOQ workbook. It contains a fictional compact 2BHK quantity example with blank rates, a linked BOQ and a trade abstract. Replace the example measurements before using it on a project.

Should wardrobes be measured in sq ft or running ft?#

Either can be an agreed quotation basis, but they describe different quantities. Front area needs width × height; a running-length quote must fix height, depth and inclusions. Neither automatically means the area of every board inside the wardrobe.

Does a kitchen running-foot rate include shutters and hardware?#

Only if the quotation explicitly says so. This example separates base and wall carcasses, shutters, countertop and a defined hardware package. Avoid adding those components again when a vendor supplies an inclusive rate.

Can I calculate an interior BOQ from the flat's floor area alone?#

Floor area supports flooring and selected ceiling quantities. Cabinet sizes need elevations, finishes need a surface schedule, and points/fixtures need counted layouts. A whole-flat per-sq-ft budget cannot supply those measurements.

Why does the workbook show no total cost at first?#

Rates are intentionally blank. It shows a trade amount only after all rates in that trade are entered, and a complete total only after all trades are priced. This keeps an incomplete quotation from looking like a finished estimate.

References and Further Reading

Primary and supporting sources cited in this article.

Tags:

boq for interior worksample boq for interior worksboq format for interior workinterior BOQinterior fit-out boq format excel