Steel calculator: how much steel a house needs

A 1,000 sq ft ground-floor RCC house needs about 4.3 t of steel, or 4.3 kg per sq ft of built-up area. A G+1 house of 1,000 sq ft a floor needs about 7.9 t. Enter your floor area, floors and foundation below for the steel by element, then work out TMT bar weights further down.

Steel for the RCC frame · 1,000 sq ft built-up · G

4.29 tonnes

4.3 kg per sq ft · 101 kg per cum of concrete · steel bill about ₹2.4 lakh at ₹56 a kg

Footings
480 kg
Plinth beams
385 kg
Columns
935 kg
Beams
1,300 kg
Slabs and sunshades
1,013 kg
Staircase and lintels
180 kg

Steel price only, before cutting, bending and fixing. For the full frame cost with concrete and shuttering, use the RCC construction cost calculator.

Steel for a house, by size

RCC-framed house on isolated footings, typical steel, M25. Built-up area is per floor.

Built-up a floorGG+1G+2
600 sq ft2.6 t · 4.3 kg/sq ft4.7 t · 3.9 kg/sq ft6.9 t · 3.8 kg/sq ft
800 sq ft3.4 t · 4.3 kg/sq ft6.3 t · 3.9 kg/sq ft9.1 t · 3.8 kg/sq ft
1,000 sq ft4.3 t · 4.3 kg/sq ft7.9 t · 3.9 kg/sq ft11.4 t · 3.8 kg/sq ft
1,200 sq ft5.2 t · 4.3 kg/sq ft9.4 t · 3.9 kg/sq ft13.7 t · 3.8 kg/sq ft
1,500 sq ft6.4 t · 4.3 kg/sq ft11.8 t · 3.9 kg/sq ft17.2 t · 3.8 kg/sq ft
2,000 sq ft8.6 t · 4.3 kg/sq ft15.7 t · 3.9 kg/sq ft22.9 t · 3.8 kg/sq ft

TMT bar weight calculator

Weight per metre is the IS 1786 nominal mass, close to d²/162 kg with d the diameter in mm. A standard bar is 12 m long.

Diameterkg per metrekg per 12 m barBars per tonne
6 mm0.2222.66375
8 mm0.3954.74211
10 mm0.6177.4135
12 mm0.88810.6594
16 mm1.57818.9453
20 mm2.46629.5934
25 mm3.85346.2422
32 mm6.31375.7613

Steel Weight Calculator (TMT Bars)

Weight of TMT reinforcement bars from diameter and length using the d²/162 formula (IS 1786 nominal mass).

Result

Unit weight (12 mm)
0.888 kg/m
Total length
120 m
Total weight
106.5 kg (0.107 t)
Cost
enter rate

Weight is the IS 1786 nominal mass, about d²/162 kg per metre where d is the diameter in mm. IS 1786 permits rolling-margin tolerance of ±7% (up to 10 mm), ±5% (12–16 mm) and ±3% (20 mm and above) on nominal mass — reconcile against weighed delivery, not just bar count.

Steel in real buildings we have measured

From BOQs we prepared from clients' structural drawings, names withheld. The calculator's typical frame uses 104 kg of steel per cum of concrete.

BuildingConcreteSteelSteel per cum
G+2 bungalow95.6 cum9.4 t98 kg
Villa180.2 cum19.9 t110 kg
G+2 shop and office382 cum32.7 t86 kg
G+1 office building667.6 cum79.6 t119 kg

More on steel: bar bending schedule (BBS) · TMT bar grades (IS 1786) · RCC construction cost calculator · cement calculator

Frequently asked questions

How much steel is required for a 1,000 sq ft house?

About 4.3 t for a 1,000 sq ft ground-floor RCC house, or 4.3 kg per sq ft of built-up area. A G+1 house of 1,000 sq ft a floor (2,000 sq ft in all) needs about 7.9 t, or 3.9 kg per sq ft. Single-storey houses use more per sq ft because the footings and plinth beams are spread over less floor area.

How much steel is used per sq ft in house construction?

3.5 to 4.5 kg per sq ft of built-up area for most RCC-framed houses on isolated footings. Our typical frame gives 3.9 kg for G+1. A raft foundation takes it to about 5.2 kg, and long spans, cantilevers or seismic zones IV and V add 15 to 20%.

What is the weight of a 12 mm TMT bar?

0.888 kg per metre, so a standard 12 m bar weighs about 10.7 kg and one tonne is about 94 bars. The site shortcut is d²/162 kg per metre, with d in mm.

How much steel goes into 1 cubic metre of RCC?

It depends on the element: slabs about 75 kg, beams about 130 kg and columns about 170 kg per cum in a typical house. Across a whole house frame it averages about 104 kg per cum. The frames we have measured from real drawings ranged from 86 to 119 kg per cum.

Why does the delivered steel weigh differently from the bar count?

IS 1786 allows a rolling margin on nominal mass: ±7% up to 10 mm, ±5% for 12 to 16 mm and ±3% from 20 mm. Buy and bill steel by weighed delivery, and keep 3 to 5% for cutting waste and laps.

How do I get the exact steel for my building?

From a bar bending schedule (BBS) worked out from your structural drawings: every bar's shape, length, number and weight, member by member. These estimates use typical ratios; your column grid, spans and seismic zone decide the real quantity.