What is a cover block in construction?
A cover block is a small spacer of concrete or PVC tied under or beside reinforcement before concreting. It holds the bars away from the formwork so the concrete cover shown on the drawing is achieved. IS 456 asks for spacers of the same size as the nominal cover, placed no more than 1 m apart.
Key facts
- Also called
- Spacer, cover spacer; chairs do the same job for top steel
- Size
- Equal to the nominal cover on the drawing (IS 456, clause 12.3.2)
- Spacing
- At most 1 m apart; closer where needed (IS 456, clause 12.3.2)
- Material
- Concrete of the same strength as the member, or PVC
What is the use of a cover block?
It keeps the reinforcement at the right distance from the concrete surface, so the steel gets the cover the designer specified for durability and fire resistance.
IS 456 asks for all reinforcement to be placed and held in the position shown on the drawings "by providing proper cover blocks, spacers, supporting bars, etc." (clause 12.2). Without them, bars sag onto the shuttering under the weight of workers and fresh concrete. The result is steel at or near the surface, which rusts, cracks the concrete and shortens the life of the member.
The cover itself is set in IS 456 clause 26.4 by exposure condition; see clear cover for the values.
What size of cover block should be used?
The same as the nominal cover the drawing specifies for that member. IS 456 says spacers between the links, or the bars where there are no links, and the formwork should be of the same nominal size as the nominal cover.
So the block size changes with the member and the exposure. IS 456 Table 16 gives minimum nominal covers of 20 mm for mild exposure, 30 mm moderate, 45 mm severe, 50 mm very severe and 75 mm extreme. It asks for at least 50 mm in footings and at least 40 mm for the main bars of columns (clauses 26.4.2.1 and 26.4.2.2). The drawing's figure governs if it is larger.
IS 456 also allows the actual cover to be up to 10 mm more than the nominal cover, but not less (clause 12.3.2). A block smaller than the cover is therefore a defect, not a tolerance.
How many cover blocks are needed for a slab?
Lay them in a grid no wider than 1 m in either direction, so the count is the number of lines each way multiplied together.
Worked example. A slab panel is 4.00 m × 3.00 m. Blocks are set in a 1.0 m grid with the first line 0.5 m in from each edge, which keeps every gap at 1 m or less.
| Direction | Lines at | Count |
|---|---|---|
| Along 4.00 m | 0.5, 1.5, 2.5, 3.5 m | 4 |
| Along 3.00 m | 0.5, 1.5, 2.5 m | 3 |
| Blocks for the panel | 4 × 3 | 12 |
Six such panels need 72 blocks. Beams and columns need blocks on their sides as well as under them, and top steel needs chairs, so count those separately. IS 456 notes that closer spacing may sometimes be necessary, for example under heavy or flexible mesh.
Concrete cover blocks vs PVC cover blocks
IS 456 accepts both: spacers and cover blocks should be of concrete of the same strength as the member, or PVC. Pieces of brick, stone or timber do not meet that rule.
| Type | Points to check |
|---|---|
| Concrete or mortar block | Strength at least that of the member; correct thickness; tie wire cast in |
| PVC spacer | Correct cover size for the bar diameter; seats firmly on the bar |
A weak block crushes under foot traffic before the pour, and the bar drops onto the formwork. Brick pieces are porous and weaker than the concrete around them.
Common mistakes with cover blocks
The usual mistakes are one block size used for every member, too few blocks, blocks missing on the sides of beams and columns, and nobody checking the cover before the pour.
- Wrong size. A 25 mm block in a footing that needs 50 mm halves the protection.
- Too few. Spacing wider than 1 m lets bars sag between blocks.
- Sides forgotten. Column and beam sides need cover as much as soffits.
- No check before the pour. Make cover blocks a line on the pour card; our shuttering guide lists the other pre-pour checks.