Clear Cover: Clear Cover / Nominal Cover

What is clear cover in construction?

Clear cover is the thickness of concrete between the outside face of a concrete member and the surface of the nearest reinforcing bar, usually the stirrup or link. IS 456 calls the design value nominal cover. It protects the steel from corrosion and fire, and its value depends on the exposure condition and the member.

Key facts

Also called
Concrete cover; IS 456 term: nominal cover
Measured to
All steel, including links (IS 456, clause 26.4.1)
Values
20 mm (mild) to 75 mm (extreme) by exposure, IS 456 Table 16; 50 mm in footings; 40 mm for column main bars
Where it appears
General notes on structural drawings, BBS cutting lengths, pre-pour checks

What is the clear cover for slab, beam, column and footing?

IS 456 sets a minimum nominal cover by exposure: 20 mm mild, 30 mm moderate, 45 mm severe, 50 mm very severe and 75 mm extreme. Footings need at least 50 mm and column main bars at least 40 mm, whatever the exposure.

CaseMinimum nominal coverIS 456 reference
Mild exposure20 mmTable 16
Moderate30 mmTable 16
Severe45 mmTable 16
Very severe50 mmTable 16
Extreme75 mmTable 16
Footings50 mm26.4.2.2
Column longitudinal bars40 mm, and not less than the bar diameter26.4.2.1

Table 16 also allows 5 mm less for main bars up to 12 mm in mild exposure, and 5 mm less in severe and very severe exposure where the concrete is M35 or above. Columns of 200 mm or less with bars not over 12 mm may use 25 mm. The cover for a required fire rating comes from Table 16A and may be larger. The structural drawing's general notes state the cover for each member; use those.

Clear cover vs nominal cover vs effective cover

Clear cover and nominal cover both run from the concrete face to the outermost steel; nominal cover is the IS 456 design value shown on drawings. Effective cover runs to the centre of the main tension bars.

TermMeasured from the concrete face toUsed for
Clear coverThe surface of the nearest barSite checks, cover block size
Nominal cover (IS 456)All steel including links; never less than the bar diameterDrawings and design
Effective coverThe centroid of the main tension barsEffective depth in design

IS 456 defines effective depth as the distance from the centroid of the tension reinforcement to the extreme compression fibre (clause 23.0). Some site notes give "clear cover to main bars" instead of cover to links. Read the general note carefully: the difference is the stirrup diameter.

How do you calculate effective cover and effective depth?

Effective cover is the nominal cover plus the link diameter, if any, plus half the main bar diameter. Effective depth is the overall depth minus the effective cover.

Slab: 125 mm thick, mild exposure with 20 mm nominal cover on the drawing, 10 mm main bars, no links. Effective cover = 20 + 10 ÷ 2 = 25 mm; effective depth = 125 − 25 = 100 mm.

Beam: 450 mm deep, moderate exposure with 30 mm nominal cover to the 8 mm stirrups, 16 mm main bars in one layer. Cover to the main bar = 30 + 8 = 38 mm; effective cover = 30 + 8 + 16 ÷ 2 = 46 mm; effective depth = 450 − 46 = 404 mm.

How is cover checked on site and in the BBS?

On site, cover blocks of the nominal cover size hold the steel, and the actual cover may exceed the nominal by up to 10 mm but never fall short. In a BBS, cover sets the bar and stirrup dimensions.

IS 456 clause 12.3.2 asks for spacers of the same nominal size as the nominal cover, placed at most 1 m apart; see cover block. Check the cover at edges, corners and column faces before the pour.

In the bar bending schedule, a stirrup's outer dimensions are the member size less the cover on each face, and straight bars stop short of the faces by the cover. Cover also enters development length and lap length checks where bars are anchored near a face.

Common mistakes with clear cover

The usual mistakes are reading cover to main bars where the drawing means cover to links, using slab cover blocks in footings and columns, and forgetting the fire-rating cover.

  • Main bar vs link. Cover to links is the IS 456 meaning; check which the note uses.
  • One size for everything. Footings need at least 50 mm; slabs in mild exposure may need 20 mm.
  • Fire cover. Table 16A can need more than Table 16.
  • No tolerance below. IS 456 allows +10 mm, not −1 mm.

Go deeper