Rohan Adira (RERA PR1330002600445): price, possession and the verified record

Rohan Adira is a 1.887-acre, 250-unit 250 project by Mandar Constructions Buildcon LLP at Panchpakahadi, registered with MahaRERA as PR1330002600445.

No conflicts found2501 approved documentsReviewed 2026-07-30
On requestPrice band
250Units registered
1.887 acRegistered area
31 Dec 2030Latest declared completion
Declared project cost

Is Rohan Adira RERA approved?

Yes. It is registered with MahaRERA under PR1330002600445, covering 1.887 acres with 250 residential units and 1 recorded approvals.

  • Building plan approval
  • AAI height clearanceNot in the reviewed filing
  • Environment clearanceNot in the reviewed filing
  • Fire scheme approvalNot in the reviewed filing
  • Consent to establishNot in the reviewed filing
  • Occupancy certificateNot expected until completion

Source: MahaRERA registration certificate PR1330002600445.

When is possession at Rohan Adira?

The record gives one declared completion date: Dec 2030. A declared date is what the promoter filed, not proof of delivery.

31 Dec 2030
binding
Original proposed completion date
This is the date displayed in the captured MahaRERA record, not a promise of possession, occupancy or final completion.
Dec 2030
weakest
Marketing / listing material · also in The promoter's own RERA filing

None of these is an occupancy certificate. A declared completion date is what the promoter filed, not proof of delivery.

Source: the promoter's RERA filing (Form REP-I) and the authority's registered-project index.

What is the price of Rohan Adira?

No price is published against this registration. Any figure you are shown should be confirmed in writing against RERA number PR1330002600445.

Source: the filed unit schedule. Price band from public listings; not promoter-confirmed.

Who is the developer of Rohan Adira?

The promoter on record is Mandar Constructions Buildcon LLP, marketed as Mandar Constructions Buildcon LLP.

Source: the authority's promoter disclosure and the filed financial schedule.

What do the approved plans for Rohan Adira show?

The layout, floor plans and elevations the promoter publishes. These are promoter-issued sheets, not documents lodged with MahaRERA — treat the dimensions on them as indicative until you see the sanctioned set.

Source: 0 filed under this registration, plus promoter-issued sheets reviewed for provenance.

Is it safe to buy in Rohan Adira?

The registration itself is sound — identity, scope and phase all check out. 3 things are still open. Resolve that before you pay.

Ongoing litigation is disclosed, without a merits conclusion
The captured project record lists three matters as ongoing: Summary Civil Suit 192/2025 in the Civil Judge (Senior Division) court, Co-operative Court matter 217/2022, and Civil Court matter 704/2022, all in Thane. The portal capture does not establish their merits, parties' current positions or outcome.
What to ask for: Obtain the current pleadings, orders, project nexus and counsel advice before relying on any legal conclusion.
A financial encumbrance is declared
The captured finance section declares an encumbrance with Tata Capital Housing Finance Ltd as lender and charge holder and lists a secured amount of 1,000,000,000. The captured data does not establish charge scope, current balance, release mechanics or CERSAI position.
What to ask for: Request lender-confirmed release, allocation and transaction-specific charge documents; do not infer title or discharge status from the portal field.
Listed documents were not locally downloaded
MahaRERA lists 21 documents, including registration, plan, title-report, Form B and July 2026 professional-certificate entries, but the local manifest shows zero downloaded files. Their filenames and portal metadata do not establish their contents.
What to ask for: Obtain and review the current primary documents, including their project/building scope, dates and signatures, before treating them as substantive support.

Source: Site Setu agent-reviewed dossier, 2026-07-30. Record-quality assessment, not investment advice.

The verified record behind this page

Every figure above comes from a document filed with MahaRERA. This is the audit that produced them — 5 dimensions assessed, every fact carrying its own confidence.

Record review

Agent-reviewed 2026-07-30 · 8 facts checked · 5 dimensions

Identity and phase scope
Supported
One registration and promoter are clearly identified
Scale and unit composition
Supported
The project schedule is mixed-use in unit composition
Timeline and construction permissions
Needs a look
The authority date is proposed, not delivery evidence
Commercial availability
Not sourced
The unit-status data is not a current offer
Legal and finance disclosures
Needs a look
Disclosures need transaction-specific follow-up
RERA registration
Pr1330002600445The MahaRERA public project record identifies Rohan Adira, project ID 64148, with registration dated 17 May 2026.
high
Legal promoter
Mandar Constructions Buildcon LLPThe retained MahaRERA record identifies this limited liability partnership as promoter; the record also lists Rohan Builders & Developers Private Limited among project professionals, which is not substituted for the promoter identity.
high
Project scope
Three buildings; 250 total unitsThe portal says the project is not in multiple phases. The schedule totals 231 residential and 19 non-residential units across Buildings A, B and C.
high
Proposed completion date
31 December 2030The captured MahaRERA record gives this as both the original and displayed proposed completion date; no extension record was returned in that capture.
high
Commencement-certificate portal entry
30 March 2026The authority record lists a commencement-certificate / NA-order entry issued to the promoter on this date. The listed underlying file was not downloaded, so its wording and scope were not reviewed.
medium
Portal unit-status snapshot
152 unsold; 98 rehab; 0 sold and 0 bookedThese labels are from the captured habitable-floor summary across all three buildings. They reconcile numerically to 250 units but are a 28 July 2026 portal snapshot, not live availability or a sales offer.
stale
Occupancy / completion certificate
Not established in reviewed materialThe retained portal index lists a registration certificate, plans and professional certificates, but no occupancy or completion certificate was identified or downloaded. This does not establish that none exists.
not-found
Current price and availability
Not independently verifiedNo dated promoter price sheet, current inventory, unit-specific quotation or agreement was reviewed. The portal unit-status snapshot is not treated as an offer.
not-found
How this review was done, and what it excluded
Authority
MahaRERA
Registration
PR1330002600445
Documents seen
1 drawing sets, 0 authority documents
3D reconstruction
Not built
Not established
Occupancy certificate, current construction progress, live inventory, dated unit-level offer

Source: MahaRERA public project record and retained portal capture, dated document index, and Site Setu editorial review

The same filings, as a working project plan

A RERA filing already contains a programme, a cost plan, an approvals register and a drawing register — just locked inside PDFs. This is that filing rendered as a live Site Setu workspace, with nothing added.

Rohan AdiraDemo · read only

Overview

Rohan Adira

From the RERA filing
1.887 ac
Registered area
1
Approvals on file
of 6 typical
1
Documents on file
plans, approvals, legal

Record timeline

  1. 31 Dec 2030Original proposed completion dateThis is the date displayed in the captured MahaRERA record, not a promise of possession, occupancy or final completion.
  2. Dec 2030Marketing possession claimweakest

Project card

Promoter
Mandar Constructions Buildcon LLP
Registration
PR1330002600445
Authority
MahaRERA
Towers
3
Units
250

This is a read-only view built from the filing. In your own workspace these become live — progress, spend and inventory update as your site team reports them.

Every value read from this project’s own filing. Where the record publishes nothing — construction progress, collections, sold inventory — the workspace shows an empty column rather than an invented number.

Other registered projects nearby

Same corridor, same authority. Compared on what is filed, not on what is advertised.

ProjectPromoterPricePossession
Rohan AdiraMandar Constructions Buildcon LLPOn request31 Dec 2030
ROHAN GRUH NIRMANM/s Rohan DevelopmentOn request — contact developer / RERA-registered sales office2018-03-31
Purva Panorama Tower DPuravankaraOn request
RUNWAL DREAMSVIJAY GURUNATH PATILOn request — contact developer / RERA-registered sales office2027-12-31
Purva PanoramaPuravankaraOn request
RUNWAL EIRENE - PART IRUNWAL DEVELOPERS LIMITEDOn request — contact developer / RERA-registered sales office2025-06-30