Brigade Sanctuary (RERA PRM/KA/RERA/1251/446/PR/041123/006372): price, possession and the verified record
Brigade Sanctuary is a 14.92-acre, 1,275-unit project by Brigade Group at Varthur Road, East Bangalore, registered with Karnataka RERA as PRM/KA/RERA/1251/446/PR/041123/006372 and listed at On request — contact developer / RERA-registered sales office.
Is Brigade Sanctuary RERA approved?
Yes. It is registered with Karnataka RERA under PRM/KA/RERA/1251/446/PR/041123/006372, covering 14.92 acres with 1,275 residential units and 6 recorded approvals.
- Building plan approval
- AAI height clearance
- Environment clearance
- Fire scheme approval
- Consent to establish
- Occupancy certificate
Source: Karnataka RERA registration certificate PRM/KA/RERA/1251/446/PR/041123/006372.
When is possession at Brigade Sanctuary?
The record gives one declared completion date: December 2024. A declared date is what the promoter filed, not proof of delivery.
None of these is an occupancy certificate. A declared completion date is what the promoter filed, not proof of delivery.
Source: the promoter's RERA filing (Form REP-I) and the authority's registered-project index.
What is the price of Brigade Sanctuary?
Publicly listed at On request — contact developer / RERA-registered sales office. No dated, unit-specific price list was sourced against this registration, so treat the band as indicative rather than an offer.
Amenities on record
- 24x7 Security with CCTV
- Power Backup
- High-Speed Passenger Lifts
- Landscaped Gardens
- Swimming Pool
- Gymnasium
- Clubhouse
- Children's Play Area
- Jogging Track
- Indoor Games Room
- Multipurpose Hall
- Ample Visitor Parking
- Rainwater Harvesting
- Fire Safety System
Source: the filed unit schedule. Price band from public listings; not promoter-confirmed.
Who is the developer of Brigade Sanctuary?
The promoter on record is Brigade Group, marketed as Brigade Group, registered at 29th Floor, World Trade Center, Brigade Gateway Campus, 26/1, Dr. Rajkumar Road, Malleswaram-Rajajinagar, Bengaluru Urban, Karnataka - 560055.
Source: the authority's promoter disclosure and the filed financial schedule.
Is it safe to buy in Brigade Sanctuary?
The registration itself is sound — identity, scope and phase all check out. 3 things are still open, and the completion date is the one field two authority sources disagree on. Resolve that before you pay.
Source: Site Setu agent-reviewed dossier, 2026-07-30. Record-quality assessment, not investment advice.
The verified record behind this page
Every figure above comes from a document filed with Karnataka RERA. This is the audit that produced them — 4 dimensions assessed, every fact carrying its own confidence.
Record review
Agent-reviewed 2026-07-30 · 8 facts checked · 4 dimensions · 1 unresolved conflict
- Registration
- K-RERA Form-C is recorded as granted on 2023-11-04, with validity through 2028-12-31.
- high
- Legal promoter
- Brigade Enterprises Limited filed as promoter; Brigade Group is a brand alias.
- high
- JDA structure
- A JDA dated 2022-08-01 is retained between individual owner Zarah Iqbal and Brigade Enterprises Limited. Terms are not treated as a title conclusion.
- high
- Site and scope
- 14.92 acres at Chikkavaderapura, Sarjapura Hobli, Anekal; 1,275 apartments in eight 2B+G+27 towers.
- high
- Plan sanction
- BDA plan reference BDA/PS/EM/E.O-1/T.A-4/E/29/2023-24 is recorded dated 2023-10-09.
- high
- Latest progress filing
- Form 5 Q1 2026-27 was submitted 2026-07-15 and reports under-construction progress; it is not completion evidence.
- high
- Date conflict
- A December 2024 completion field conflicts with ongoing status, a December 2028 RERA-possession field and a separate December 2027 developer target.
- conflicting
- Inventory snapshot
- The retained portal snapshot says 1,275 booked and 0 available; this is a filing/portal snapshot, not proof that no current seller inventory exists.
- stale
▸ How this review was done, and what it excluded
- Authority
- Karnataka RERA
- Registration
- PRM/KA/RERA/1251/446/PR/041123/006372
- Documents seen
- 0 drawing sets, 5 authority documents
- 3D reconstruction
- Not built
- Not established
- Occupancy certificate, current construction progress, live inventory, dated unit-level offer
Source: K-RERA Form-C, JDA, BDA plan and Q1 2026-27 professional filing
The same filings, as a working project plan
A RERA filing already contains a programme, a cost plan, an approvals register and a drawing register — just locked inside PDFs. This is that filing rendered as a live Site Setu workspace, with nothing added.
Overview
Brigade Sanctuary
Record timeline
- December 2024Marketing possession claimweakest
Project card
- Promoter
- Brigade Group
- Registration
- PRM/KA/RERA/1251/446/PR/041123/006372
- Authority
- Karnataka RERA
- Units
- 1,275
This is a read-only view built from the filing. In your own workspace these become live — progress, spend and inventory update as your site team reports them.
Every value read from this project’s own filing. Where the record publishes nothing — construction progress, collections, sold inventory — the workspace shows an empty column rather than an invented number.
Other registered projects nearby
Same corridor, same authority. Compared on what is filed, not on what is advertised.
| Project | Promoter | Price | Possession |
|---|---|---|---|
| Brigade Sanctuary | Brigade Group | On request — contact developer / RERA-registered sales office | — |
| Brigade Valencia Phase 1 (Cielo) | Brigade Group | On request — contact developer / RERA-registered sales office | 31/12/2027 (per RERA Form-C) |
| Brigade Valencia Phase 2 | Brigade Group | On request — contact developer / RERA-registered sales office | Sep 2029 (RERA proposed); 2028 (developer target) |
| Brigade Calista Phase 1 | Brigade Group | On request — contact developer / RERA-registered sales office | 2026 (expected) |
| Brigade Calista Phase 2 | Brigade Group | On request — contact developer / RERA-registered sales office | 2027 (expected) |
| Brigade Oasis Phase 1 | Brigade Group | On request — contact developer / RERA-registered sales office | 30/06/2026 (Section 6 extension; original 30/06/2025) |