Marvel Cascada D building (RERA P52100003507): price, possession and the verified record
Marvel Cascada D building is a 0.381-acre, 00 project by MARVEL SIGMA HOMES PRIVATE LIMITED at Pune (M Corp.), registered with MahaRERA as P52100003507 and listed at On request — contact developer / RERA-registered sales office.
Is Marvel Cascada D building RERA approved?
Yes. It is registered with MahaRERA under P52100003507, covering 0.381 acres0 and 6 recorded approvals.
- Building plan approval
- AAI height clearance
- Environment clearance
- Fire scheme approval
- Consent to establish
- Occupancy certificate
Source: MahaRERA registration certificate P52100003507.
When is possession at Marvel Cascada D building?
The record gives one declared completion date: Oct 2019. A declared date is what the promoter filed, not proof of delivery.
None of these is an occupancy certificate. A declared completion date is what the promoter filed, not proof of delivery.
Source: the promoter's RERA filing (Form REP-I) and the authority's registered-project index.
What is the price of Marvel Cascada D building?
Publicly listed at On request — contact developer / RERA-registered sales office for 0. No dated, unit-specific price list was sourced against this registration, so treat the band as indicative rather than an offer.
Amenities on record
- 24x7 Security with CCTV
- Power Backup
- High-Speed Passenger Lifts
- Landscaped Gardens
- Swimming Pool
- Gymnasium
- Clubhouse
- Children's Play Area
- Jogging Track
- Indoor Games Room
- Multipurpose Hall
- Ample Visitor Parking
- Rainwater Harvesting
- Fire Safety System
Source: the filed unit schedule. Price band from public listings; not promoter-confirmed.
Who is the developer of Marvel Cascada D building?
The promoter on record is Marvel Sigma Homes Private Limited, marketed as MARVEL SIGMA HOMES PRIVATE LIMITED.
Source: the authority's promoter disclosure and the filed financial schedule.
Is it safe to buy in Marvel Cascada D building?
The registration itself is sound — identity, scope and phase all check out. 3 things are still open. Resolve that before you pay.
Source: Site Setu agent-reviewed dossier, 2026-07-30. Record-quality assessment, not investment advice.
The verified record behind this page
Every figure above comes from a document filed with MahaRERA. This is the audit that produced them — 4 dimensions assessed, every fact carrying its own confidence.
Record review
Agent-reviewed 2026-07-30 · 6 facts checked · 4 dimensions
- Status
- The MahaRERA public record displays Lapsed.
- high
- Promoter and building
- Marvel Sigma Homes Private Limited is the promoter; D is the single recorded 21-floor building at Survey Nos. 28 and 29.
- high
- Unit schedule
- Three 3.5BHK rows total 32 homes. The historic table is not availability evidence.
- high
- Programme
- Registration is dated 2017-08-05; the original completion field is 2018-10-31 and revised field 2019-10-31.
- high
- Completion-file boundary
- Completion D is indexed 2019-02-13, with historic architect/engineer filings. Its certificate content and OC scope are not established.
- high
- Proceedings
- Seven complaints, a 2019 submitted appeal and a non-compliance row are displayed without final outcomes.
- not-reported
▸ How this review was done, and what it excluded
- Authority
- MahaRERA
- Registration
- P52100003507
- Documents seen
- 0 drawing sets, 0 authority documents
- 3D reconstruction
- Not built
- Not established
- Occupancy certificate, current construction progress, live inventory, dated unit-level offer
Source: MahaRERA public project record and retained D-building plan, title, progress and indexed completion-file disclosures
The same filings, as a working project plan
A RERA filing already contains a programme, a cost plan, an approvals register and a drawing register — just locked inside PDFs. This is that filing rendered as a live Site Setu workspace, with nothing added.
Overview
Marvel Cascada D building
Record timeline
- Oct 2019Marketing possession claimweakest
Project card
- Promoter
- Marvel Sigma Homes Private Limited
- Registration
- P52100003507
- Authority
- MahaRERA
- Towers
- 1
This is a read-only view built from the filing. In your own workspace these become live — progress, spend and inventory update as your site team reports them.
Every value read from this project’s own filing. Where the record publishes nothing — construction progress, collections, sold inventory — the workspace shows an empty column rather than an invented number.
Other registered projects nearby
Same corridor, same authority. Compared on what is filed, not on what is advertised.
| Project | Promoter | Price | Possession |
|---|---|---|---|
| Marvel Cascada D building | MARVEL SIGMA HOMES PRIVATE LIMITED | On request — contact developer / RERA-registered sales office | — |
| Marvel Kyra A AND B Building | MARVEL SIGMA HOMES PRIVATE LIMITED | On request — contact developer / RERA-registered sales office | 2021-12-30 |
| Marvel Basilo A AND B Building | MARVEL SIGMA HOMES PRIVATE LIMITED | On request — contact developer / RERA-registered sales office | 2027-12-31 |
| Marvel Cascada C Building | MARVEL SIGMA HOMES PRIVATE LIMITED | On request — contact developer / RERA-registered sales office | 2018-06-30 |
| Marvel Cascada E Building | MARVEL SIGMA HOMES PRIVATE LIMITED | On request — contact developer / RERA-registered sales office | 2022-04-30 |
| Marvel Bounty J Building | MARVEL SIGMA HOMES PRIVATE LIMITED | On request — contact developer / RERA-registered sales office | 2025-08-06 |