Who Does What: The Roles on a Building Project

Lesson 2 of 18 · 7 min read

A building is made by many hands. Most problems on site are not about skill. They are about hand-offs: one person assumed the other had the latest drawing, or the rate, or the decision.

So it helps to know who does what, and exactly what each person passes on.

The roles

Lesson data table
RoleMain jobCommon toolsHands over
Owner / clientSets the brief and budget, takes decisions, paysPhone, WhatsApp, ExcelBrief, approvals, payments
ArchitectLayout, look, municipal approvalsAutoCAD, SketchUp, Revit or Archicad, a render enginePlans, sections, elevations, renders
Structural engineerMakes it stand up safelyETABS, SAFE, STAAD.Pro, AutoCAD, ExcelGA and reinforcement drawings, BBS
MEP consultantPower, water, drainage, fire, air-conditioningAutoCAD or Revit, HAP, DIALux evo, ETAPServices layouts, load and size calculations
QS / estimatorHow much, at what costExcel, Bluebeam Revu, CostX, SOR booksBOQ, rate analysis, RA bills
PlannerSequence and timeMicrosoft Project, Primavera P6Programme, look-ahead plans
Contractor / site engineerBuilds it and measures itDrawings on phone, WhatsApp, site apps, ExcelDPRs, measurement book, bills
Thekedar (labour contractor)Supplies and runs a gang for one tradePhone, a notebookLabour, daily work, his bill
Interior designerFinishes, furniture, lightingSketchUp, 3ds Max, AutoCADConcept deck, shop drawings, material list
Modular factoryMakes kitchens, wardrobes, panelsFactory design software such as Cabinet Vision or imos, CNCCut lists, CNC files, installation drawings

App names here are common examples, not a full list or a recommendation. Many small offices use just AutoCAD and Excel for everything.

Who is busy when

The matrix below shows a typical pattern. A filled dot means main work in that stage. A hollow dot means the person reviews, answers queries or takes part.

Who is busy at which stage. A typical pattern, not a rule. On a small house the architect may also do the estimate, and the contractor may also plan. On a large job each dot can be a whole team.

Notice two things. The architect has the longest line: from brief to handover, as designer and then as the person who answers site queries. And the QS has two peaks: the estimate before work starts, and the bills while work goes on.

On a small Indian site

On a house or a small builder's project, one person often wears several hats.

  • The architect may also prepare the structural drawings through an associate engineer.
  • The contractor may do the estimate, the schedule and the billing.
  • The owner may act as project manager, buying cement and steel directly.
  • Each trade (shuttering, bar bending, masonry, plaster, tiles) may be run by a separate thekedar, paid per sq ft or per day.

None of this is wrong. But when one person holds many roles, the hand-offs become invisible. Nobody writes down which drawing the bar bender used, or which rate the tile thekedar agreed. That is where disputes start.

A worked example: one decision, five people

The owner wants a larger window in the living room, 1.8 m wide instead of 1.2 m.

  1. Architect revises the plan and elevation. Revision R2.
  2. Structural engineer checks the lintel and the beam above. The lintel goes from 150 mm to 230 mm deep.
  3. QS updates the BOQ. More aluminium window, less brickwork, a bigger lintel.
  4. Contractor updates the order for the window frame and tells the masonry thekedar.
  5. Owner approves the cost change.

Say the change adds 0.72 sq m of window at ₹6,500 per sq m (₹4,680), removes about 0.17 m³ of 230 mm brickwork at ₹7,650 per m³ (₹1,270), and adds a little lintel concrete and steel (say ₹900). The net extra is about ₹4,300. Small money. But if step 2 is skipped and the old lintel is cast, fixing it later costs far more. These rates are illustrative.

Common failure points

  • Drawing sent to one person only. The architect sends R2 to the owner on WhatsApp. The site keeps building from R1.
  • Verbal rate agreements. The thekedar's rate is agreed on a call and remembered differently at billing time.
  • No owner for a decision. Everyone assumes someone else told the structural engineer.

What comes next

People hand over information. The gates decide when that information is final. That is the next lesson.

Key takeaways

  • Most site problems are hand-off problems, not skill problems.
  • Each role hands over specific outputs: drawings, calculations, BOQs, programmes, DPRs or cut lists.
  • The architect is involved from brief to handover; the QS peaks at the estimate and during billing.
  • On small sites one person may hold several roles, which hides hand-offs. Write them down.
  • One design change can touch five people. Check each of them got it.

Verify on site

  • Make a one-page contact list: each role, the person, and what they send you.
  • For the last design change, confirm that the structural engineer, QS and contractor all received it.
  • Put every thekedar rate in writing, even as a WhatsApp message.

Check your understanding

3 questions. Answering them marks this lesson complete — results stay on your device.

  1. 1. Who normally prepares the bar bending schedule (BBS)?
  2. 2. On a small site, why is it risky when one person holds several roles?
  3. 3. The owner widens a window. Who must check the lintel before it is cast?