A bill of quantities (BOQ) is a list of work items. Each line has a description, a unit, a quantity and a rate. Quantity x rate = amount. The sum of the amounts is the estimate.

The quantity comes from takeoff. The rate comes from one of three places.

Where rates come from

  • CPWD DSR. The Central Public Works Department publishes the Delhi Schedule of Rates, with detailed item descriptions and rates for Delhi. Many central government works use it, with a cost index for other locations.
  • State PWD SORs. Most states publish their own schedule of rates, often updated every year or two. State government works and many local bodies use them.
  • Market rates. Private projects usually work from current quotes for materials and labour, sometimes using SOR descriptions as a template.

SOR rates are a reference. They may lag the market, and they may or may not include GST, depending on the SOR. Always read its general notes.

Rate analysis: how a rate is built

A rate analysis breaks one unit of work into materials, labour, equipment, and overheads and profit. Here is an illustrative analysis for 1 m³ of 230 mm brick masonry in cement mortar 1:6. The quantities follow common practice; the prices are illustrative 2026 figures and will differ in your city.

Lesson data table
ComponentQuantityRateAmount
Bricks (modular)500 nos₹8.50 each₹4,250
Cement for mortar1.31 bags₹380 per bag₹498
Sand for mortar0.272 m³₹2,000 per m³₹544
Mason0.7 day₹900 per day₹630
Helper (beldar)1.0 day₹600 per day₹600
Water, scaffolding, small tools2%₹130
Cost of work₹6,652
Overheads and profit15%₹998
Rate per m³₹7,650

Where do the mortar numbers come from? About 0.25 m³ of wet mortar per m³ of brickwork. Dry volume is about 1.27 times wet, so 0.3175 m³. In a 1:6 mix, cement is one part in seven: 0.0454 m³, or about 65 kg, which is 1.31 bags of 50 kg. Sand is six parts in seven: 0.272 m³.

CPWD analyses commonly add 15% for the contractor's overheads and profit. Private contractors may use a different figure.

From rate to BOQ line

Now the BOQ line:

Lesson data table
ItemDescriptionUnitQtyRateAmount
4.1Brick masonry 230 mm thick in CM 1:6, superstructure up to floor 2m³42.50₹7,650₹3,25,125

The quantity 42.50 m³ comes from the measurement sheet. The rate comes from the analysis. Anyone can check both.

What makes a good BOQ

  • Clear descriptions. Material, mix, thickness, location and what is included (scaffolding, curing, cleaning).
  • Units that match IS 1200. m³ for masonry and concrete, m² for plaster and flooring, kg or tonne for steel, numbers for doors.
  • Traceable quantities. Every quantity links to a measurement sheet.
  • Stated assumptions. Anything not on the drawings is written down.
  • A rate basis. Which SOR, which market quotes, which date.

Common mistakes

  • Mixing SOR rates from different years.
  • Forgetting that some SOR rates exclude GST.
  • Copying a rate from another city without adjusting labour and sand prices.
  • Pricing items the drawings do not show, or missing items they do.

What comes next

A priced BOQ goes out to tender. After award, the same BOQ becomes the basis for running bills. That is the next lesson.

Key takeaways

  • A BOQ line is quantity x rate; quantities come from takeoff, rates from SOR, DSR or the market.
  • CPWD DSR and state PWD SORs are reference rates; read their notes on GST and location.
  • A rate analysis builds one unit from materials, labour, sundries, and overheads and profit.
  • In the example, 1 m³ of 230 mm brickwork in CM 1:6 comes to an illustrative ₹7,650.
  • Good BOQs have clear descriptions, IS 1200 units, traceable quantities and stated assumptions.

Verify on site

  • For each major BOQ item, keep the rate analysis and the date of the rates used.
  • Check whether your SOR rates include or exclude GST.

Check your understanding

3 questions. Answering them marks this lesson complete — results stay on your device.

  1. 1. What is the DSR?
  2. 2. In a 1:6 cement mortar, what share of the dry volume is cement?
  3. 3. A BOQ line has 42.50 m³ at ₹7,650 per m³. What is the amount?