MEP Design, Clash Coordination and the CDE
Lesson 8 of 18 · 7 min read
MEP means mechanical, electrical and plumbing. In practice it covers power and lighting, water supply, drainage, fire fighting, air-conditioning and ventilation, and low-voltage systems like CCTV and networking.
Services must fit inside a building that the architect and structural engineer have already shaped. That is why coordination is a separate job.
How services are designed
Each service has two kinds of work: calculations and layouts.
| Service | Calculations | Example tools | Layout output |
|---|---|---|---|
| Electrical | Loads, cable sizes, short circuit | ETAP, Excel | Power and lighting layouts, single-line diagram |
| Lighting | Lux levels | DIALux evo | Fixture layouts |
| HVAC | Heat load, duct and pipe sizes | HAP, Excel | Duct and piping layouts |
| Plumbing and drainage | Fixture units, pipe sizes, slopes | Excel, pipe-flow tools | Water and drainage layouts, sections |
| Fire | Sprinkler and hydrant sizing | Hydraulic tools, Excel | Fire layouts |
Layouts are drawn in AutoCAD on most Indian houses and mid-size jobs, often by the MEP contractor rather than a separate consultant. On larger projects, services are modelled in Revit so they can be checked in 3D.
What a clash is
A clash is two things trying to occupy the same space. Classic examples:
- A 600 x 400 mm duct running through a 600 mm deep beam.
- A drainage pipe that needs a slope but hits a beam halfway along.
- An electrical conduit cluster where a sleeve was never left in the slab.
On a 2D project, clashes are found on site, when someone is standing on a ladder with a duct section in hand. On a coordinated 3D project, they are found on screen weeks earlier.
Clash detection
Clash detection software overlays the architecture, structure and MEP models and reports every place they collide.
- Common tools: Navisworks, Solibri, Revizto.
- Output: a clash report. Each clash has a location, the two elements, the overlap, an owner and a status.
Not every clash is real. A pipe touching insulation may be fine. The coordinator groups clashes, discards false ones, and assigns the real ones to the right consultant.
The common data environment (CDE)
A CDE is one controlled place where every team puts its drawings and models, with clear states: work in progress, shared, published and archived. The idea comes from the ISO 19650 series on managing information in BIM projects.
Examples of CDE platforms include Autodesk Forma (Autodesk renamed Autodesk Construction Cloud to Forma in March 2026; its file store, formerly Autodesk Docs, is now Forma Data Management; BIM 360 continues as an older product), Trimble Connect, and similar platforms from other vendors.
On many Indian small and mid-size projects, the CDE is in practice a shared Google Drive or a WhatsApp group. That can work if one person owns the folder and nobody builds from a forwarded copy.
A worked example: the cost of a missed sleeve
A G+4 commercial building has 12 places where drainage and AC drain pipes must cross beams. On a 2D job, sleeves were not shown on the structural drawings. They are found after casting.
- Core cutting through each beam: about ₹1,500 per hole (illustrative), so 12 x ₹1,500 = ₹18,000.
- Structural engineer's check of each cut location, and possible strengthening: more fees and delay.
- Worse: some cuts may not be allowed at all, forcing reroutes with extra bends and false ceiling height lost.
The same 12 sleeves, shown on the GFC structural drawings, cost a few hundred rupees each in PVC pipe pieces before the pour.
What comes next
Module 4 turns to money: how quantities are measured from drawings or models, and how they become a priced BOQ.
Key takeaways
- MEP design has two parts: calculations (loads, sizes) and layouts.
- A clash is two elements wanting the same space; detection finds it on screen, not on site.
- Clash reports need grouping and owners; not every clash is real.
- A CDE is one controlled store with states: work in progress, shared, published, archived.
- Sleeves shown before casting cost little; holes cut after casting cost much more.
Verify on site
- Before each slab pour, check sleeves and inserts against the latest MEP layouts.
- Name one person who owns the project's shared drawing folder.
Check your understanding