Skip to main content

Worked Example: Budget for a G+1 Duplex

Lesson 32 of 60 · 6 min read

This lesson builds one document end to end: the budget an owner can sanction, a bank can lend against, and a site engineer can track — for the duplex this module has carried from Lesson 1. Every number is computed, every provision has a rule, and the whole thing fits on three pages. Work through it once with these numbers, then rebuild it with your own project's; the structure is the skill.

The project

  • Plot: 30 × 40 ft (1,200 sq ft), tier-2 city outskirts, ordinary soil.
  • Building: G+1 duplex, RCC framed, 800 sq ft per floor — 1,600 sq ft built-up.
  • Specification: standard finish — vitrified tiles, granite kitchen, branded wiring and sanitaryware, emulsion paint.
  • Schedule: 12 months, starting after monsoon to keep slab casts out of the sand-restriction window.
  • Delivery model: owner-managed — owner buys material on dealer accounts, a thekedar executes civil work on labour rates, specialist trades contracted per point/fixture.
  • Financing: construction loan sanctioned ₹27,00,000; balance owner equity.

All rates are indicative mid-2026; rebuild with your city's current quotations.

Step 1 — Thumb-rule sanity check

Competitive quotes put standard finish at ₹1,950 – 2,350 per sq ft; the detailed estimate (Modules 2–4 methods) prices the drawings at ₹33,60,000, i.e. ₹2,100 per sq ft — inside the standard band of ₹2,000 – 2,600. The estimate passes the band check; had it landed at ₹1,600 or ₹3,000 for this spec, the estimate — not the band — would get re-audited.

Step 2 — Base cost: everything the sq-ft rate hides

Lesson data table
LineAmount
A. Construction (civil + finishes, detailed estimate)₹33,60,000
B. External works: compound wall, gate, paving, borewell, sump, septic/sewer connection₹2,40,000
C. Statutory: plan sanction, approvals, water and power connections₹60,000
D. Design: architect + structural engineer (about 3%)₹1,00,000
Base cost (A+B+C+D)₹37,60,000

Line C varies sharply by municipality — put your local body's actual fee schedule here, not an allowance.

Step 3 — Contingency (risk-table derived, Lesson 4)

Named risks × probability × impact = ₹1,88,000 (5.0% of base). Held in its own line, spent only through the contingency register.

Step 4 — Escalation provision

12-month schedule, 6% p.a. assumed input drift: 37,60,000 × 0.06 × 0.5 = ₹1,12,800 (3.0%). Drawn only against documented price differences on unbought quantities.

Step 5 — The sanctionable budget

Lesson data table
ComponentAmountShare
Base cost₹37,60,00092.6%
Contingency₹1,88,0004.6%
Escalation₹1,12,8002.8%
Total budget₹40,60,800100%
The complete duplex budget: ₹40.61 lakh, fully derived. Every component of the sanctionable budget for the 1,600 sq ft G+1 duplex. Base components in blue; risk provisions distinguished. Indicative mid-2026 figures.

Effective cost: ₹2,538 per sq ft — 21 percent above the naked thumb rate, every rupee of the difference named. This is the total the family plans against and the number quoted to the bank. (If you are comparing against buying a flat instead: developer prices quote on RERA-defined carpet area, this budget is on built-up area — convert before comparing, or the flat will look falsely expensive.)

Step 6 — Stage plan (construction cost, from Lesson 2)

Foundation and plinth 12% (₹4,03,200) · RCC frame 24% (₹8,06,400) · masonry 10% (₹3,36,000) · plaster and waterproofing 8% (₹2,68,800) · flooring 10% (₹3,36,000) · doors-windows 9% (₹3,02,400) · electrical 7% (₹2,35,200) · plumbing 7% (₹2,35,200) · painting 6% (₹2,01,600) · site development and handover 7% (₹2,35,200). Sums to exactly ₹33,60,000 — the reconciliation identity that makes variance tracking possible.

Step 7 — Cash flow by quarter

Rolling up the monthly projection from Lesson 5, plus the timing of the non-construction lines (design fees early, external works late):

Lesson data table
QuarterConstruction outflowNon-construction outflowNotes
Q1 (m1–3)₹5,71,200 (17%)₹1,30,000Design fees, approvals, foundation
Q2 (m4–6)₹11,08,800 (33%)₹20,000Both slabs — peak burn ₹4.03 L/month
Q3 (m7–9)₹10,75,200 (32%)₹30,000Frame tops out, masonry, plaster
Q4 (m10–12)₹6,04,800 (18%)₹2,20,000Finishes + external works
Total₹33,60,000₹4,00,000Provisions drawn as events occur

Step 8 — Bank tranche mapping

Loan ₹27,00,000 (75% of construction + external works, ₹36 lakh). Indicative tranche schedule agreed with the lender — always confirm your bank's own slabs in writing:

Lesson data table
TrancheTrigger (verified by bank engineer)AmountExpected timing
T1 (20%)Foundation complete₹5,40,000Month 3
T2 (25%)Plinth, GF columns and slab₹6,75,000Month 5
T3 (30%)FF roof slab cast₹8,10,000Month 7
T4 (15%)Masonry, plaster, doors-windows₹4,05,000Month 10
T5 (10%)Completion certificate₹2,70,000Month 12+

Owner equity covers the balance: 40,60,800 − 27,00,000 = ₹13,60,800, deployed first (banks disburse after owner margin is visible in the work) plus the ₹5 – 6 lakh peak-burn float from Lesson 5. Note T5: the last ₹2.7 lakh arrives only with the completion certificate — plan Q4 finishing cash from your own float, not from T5.

Running the budget: the three-column habit

From day one, every stage carries three numbers: planned (this document), committed (orders placed, agreements signed), and spent (bills certified). Example from month 3 of this build:

Lesson data table
StagePlannedCommittedSpentStatus
Foundation and plinth₹4,03,200₹4,21,000₹4,21,000Closed: +₹17,800 (+4.4%) — extra excavation depth on east side; drawn from contingency, register entry #1
RCC frame₹8,06,400₹3,10,000₹1,85,000Steel for both slabs booked at ₹61.8/kg — locks escalation exposure

The variance rule: any stage drifting past 2 percent gets explained in writing the month it happens, and the remaining budget is re-forecast. Twelve small course corrections beat one year-end shock.

How this file protects your money

The finished budget is not just arithmetic — it is the evidence architecture for the whole build. Concretely: the signed rate-and-inclusions page (Lesson 1) plus this budget defeats the "that was extra" claim; the stage completion definitions and dated photos (Lesson 2) move bank tranches and settle thekedar bills; the challan-matched material records (Lesson 3) kill both dealer over-billing and "material extra" claims; the contingency register and base-price schedule (Lesson 4) turn price-spike standoffs into arithmetic; the planned-vs-actual S-curve (Lesson 5) proves who delayed what. If a dispute ever escalates — consumer forum, arbitration, or just a hard negotiation — the party holding this file states facts while the other side tells stories. That asymmetry, built in one hour a month, is the real return on this module.

Common mistakes at assembly

  • Sanctioning the base cost instead of the total. A family that plans ₹37.6 lakh has already decided its provisions will become debt.
  • Quoting the bank a different number than the family plans. One budget, one total; the loan estimate and household plan must be the same document.
  • Skipping the re-forecast. A budget last updated at month one is archaeology by month eight.
  • Letting the provisions merge. The day contingency and escalation blur into "the buffer", both rules die.

Where this goes next

The budget tells you what everything should cost. Making reality obey it — supplier rate tracking, quotation comparison, PO discipline and material reconciliation — is cost control, and it is the whole of the next module.

Key takeaways

  • A bank-ready budget has five derived layers: construction estimate, non-construction base lines, contingency, escalation, and a stage plan that reconciles to the total exactly.
  • The duplex lands at ₹40,60,800 — ₹2,538 per sq ft effective, 21 percent above the thumb rate, with every rupee of the difference named and ruled.
  • Map loan tranches to verified stages and plan Q4 finishing from your own float — the completion tranche arrives after the money was needed.
  • Run every stage with three columns — planned, committed, spent — and explain any drift past 2 percent in the month it happens.
  • Early procurement locks escalation exposure: steel booked at month 3 rates removes the largest single price risk from the budget.
  • The budget file doubles as your evidence architecture — the party holding dated records states facts in a dispute; the other side tells stories.

Verify on site

  • Reconcile the stage plan to the construction estimate to the rupee before sanctioning the budget.
  • Confirm the lender's tranche triggers in writing and align stage completion definitions to them.
  • Deploy owner equity first and keep the peak-burn float untouched by early enthusiasm.
  • Update planned/committed/spent for every stage on a fixed monthly date.
  • Record every contingency and escalation drawdown in its register the day it happens.
  • Re-forecast the remaining budget after every stage closure and re-issue the one-page summary to everyone who funds or builds.

Check your understanding

5 questions. Answering them marks this lesson complete — results stay on your device.

  1. 1. The duplex base cost is ₹37,60,000, contingency ₹1,88,000 and escalation ₹1,12,800. The sanctionable budget is:
  2. 2. Why should Q4 finishing be funded from owner float rather than the final loan tranche?
  3. 3. At month 3, foundation closed at ₹4,21,000 against a plan of ₹4,03,200 due to extra excavation depth. The correct booking is:
  4. 4. The budget quotes ₹2,538 per sq ft on built-up area. A developer's flat nearby quotes ₹4,200 per sq ft. Before comparing, you must:
  5. 5. What makes a stage-wise budget 'bank-ready'?

Want the free certificate?

The whole course is free and open — no signup needed to learn. Enter your details only if you want us to track your progress on this device and issue a named certificate after the final assessment.