Trimurty Divinity (RERA RAJ/P/2021/1622): price, possession and the verified record
Trimurty Divinity is a 0.6218-acre, 59-unit project by Trimurty Builders at Malviya Marg, C-Scheme, registered with Rajasthan RERA as RAJ/P/2021/1622 and listed at On request — contact developer / RERA-registered sales office. Possession is the one thing the record does not agree on: the promoter’s own filing declares 31 Mar 2026, the authority’s current record shows See RERA portal for latest declared completion date.
Is Trimurty Divinity RERA approved?
Yes. It is registered with Rajasthan RERA under RAJ/P/2021/1622, covering 0.6218 acres with 59 residential units and 6 recorded approvals.
- Building plan approval
- AAI height clearance
- Environment clearance
- Fire scheme approval
- Consent to establish
- Occupancy certificate
Source: Rajasthan RERA registration certificate RAJ/P/2021/1622.
When is possession at Trimurty Divinity?
There are 2 different dates on record. The promoter committed to 31 Mar 2026 in its own RERA filing. The authority’s current public record shows See RERA portal for latest declared completion date.
None of these is an occupancy certificate. A declared completion date is what the promoter filed, not proof of delivery. What to ask for: Request the latest RERA status, construction update, extension/restoration order if any, and phase/building-specific OC or CC before relying on completion language.
Source: the promoter's RERA filing (Form REP-I) and the authority's registered-project index.
What is the price of Trimurty Divinity?
Publicly listed at On request — contact developer / RERA-registered sales office. No dated, unit-specific price list was sourced against this registration, so treat the band as indicative rather than an offer.
Amenities on record
- 24x7 Security with CCTV
- Power Backup
- High-Speed Passenger Lifts
- Landscaped Gardens
- Swimming Pool
- Gymnasium
- Clubhouse
- Children's Play Area
- Jogging Track
- Indoor Games Room
- Multipurpose Hall
- Ample Visitor Parking
- Rainwater Harvesting
- Fire Safety System
Source: the filed unit schedule. Price band from public listings; not promoter-confirmed.
Who is the developer of Trimurty Divinity?
The promoter on record is TRIMURTY COLONIZERS AND BUILDERS PRIVATE LIMITED Partnership Firm, marketed as Trimurty Builders, registered at 601 Geeta Enclave, Vinoba Marg, C-Scheme, Jaipur, Rajasthan - 302001.
Source: the authority's promoter disclosure and the filed financial schedule.
What do the approved plans for Trimurty Divinity show?
The layout, floor plans and elevations as filed. Every sheet below is rendered from a document the promoter lodged with Rajasthan RERA, and opens to the original upload — nothing here is a brochure render.
Source: the 26 documents filed under this registration.
Is it safe to buy in Trimurty Divinity?
The registration itself is sound — identity, scope and phase all check out. 3 things are still open. Resolve that before you pay.
Source: Site Setu agent-reviewed dossier, 2026-07-30. Record-quality assessment, not investment advice.
The verified record behind this page
Every figure above comes from a document filed with Rajasthan RERA. This is the audit that produced them — 4 dimensions assessed, every fact carrying its own confidence.
Record review
Agent-reviewed 2026-07-30 · 7 facts checked · 4 dimensions
- RERA registration
- Raj/P/2021/1622The retained Form-A certificate identifies Trimurty Divinity and records registration on 30 August 2021.
- high
- Registered promoter
- Trimurty Colonizers and Builders Private LimitedThe retained certificate and filing record identify the legal promoter; Trimurty Builders/Group is marketing context.
- high
- Registered building scope
- 59 apartments on about 0.6218 acreThe retained RERA-derived record and revised plan describe one group-housing building at Plot C-33, Malviya Marg.
- high
- Governing plan form
- LB + UB + stilt + 12 floorsThe JMC Heritage revision dated February 2023 is the retained governing plan record; the older 11-floor sanction is not used as the final described form.
- high
- Extension horizon
- 31 March 2026The retained Form-F granted a 12-month extension from 1 April 2025 to 31 March 2026. It is a registration-validity event, not a completion certificate.
- stale
- Occupancy and completion certificate
- Not establishedNo project-scoped OC or completion certificate was identified in the retained certificate, extension and sanctioned-plan bundle. This does not establish that such a certificate was never issued.
- not-found
- Booking, price and availability
- Not independently verified as currentA 2023 affidavit reported five bookings at that time; aggregator price and completion labels are not current, unit-specific commercial evidence.
- stale
▸ How this review was done, and what it excluded
- Authority
- Rajasthan RERA
- Registration
- RAJ/P/2021/1622
- Documents seen
- 17 drawing sets, 9 authority documents
- 3D reconstruction
- Not built
- Not established
- Occupancy certificate, current construction progress, live inventory, dated unit-level offer
Source: Retained Rajasthan RERA certificate, Form-F extension, promoter filings and JMC sanctioned-plan records
The same filings, as a working project plan
A RERA filing already contains a programme, a cost plan, an approvals register and a drawing register — just locked inside PDFs. This is that filing rendered as a live Site Setu workspace, with nothing added.
Overview
Trimurty Divinity
Record timeline
- 31 Mar 2026Form-F extension validity endThe retained extension runs to this date; no later extension, close-out or occupancy finding was established.
- See RERA portal for latest declared completion dateThe promoter's own RERA filingDeclared by the promoter in Form REP-I — the strongest commitment on record.
Project card
- Promoter
- TRIMURTY COLONIZERS AND BUILDERS PRIVATE LIMITED Partnership Firm
- Registration
- RAJ/P/2021/1622
- Authority
- Rajasthan RERA
- Units
- 59
This is a read-only view built from the filing. In your own workspace these become live — progress, spend and inventory update as your site team reports them.
Every value read from this project’s own filing. Where the record publishes nothing — construction progress, collections, sold inventory — the workspace shows an empty column rather than an invented number.
Other registered projects nearby
Same corridor, same authority. Compared on what is filed, not on what is advertised.
| Project | Promoter | Price | Possession |
|---|---|---|---|
| Trimurty Divinity | Trimurty Builders | On request — contact developer / RERA-registered sales office | See RERA portal for latest declared completion date |
| Trimurty Bani Park Project | Trimurty Builders | On request — contact developer / RERA-registered sales office | — |
| Trimurty Kachnar | Trimurty Builders | On request — contact developer / RERA-registered sales office | — |
| Trimurty The Greater Jagatpura | Trimurty Builders | On request — contact developer / RERA-registered sales office | — |
| Trimurty Valeria | Trimurty Builders | On request — contact developer / RERA-registered sales office | — |
| Times Estate Phase I | Times Estate | On request | 2027-12-31 |