Sample programmes: a river bridge in P6 and a 21-storey tower

Two complete construction schedules, built the way we build yours: networked logic, Indian calendars with monsoon windows, contract milestones, and every duration traced to a quantity and a named norm. Read them here, download the PDF extracts, or ask for the native files.

Primavera P6 · illustrative sample

River bridge on piles, NH EPC package

A two-lane major bridge of 8 spans of 40 m on bored piles, programmed the way the NHAI EPC Agreement asks: networked logic, Schedule-J milestones and a monthly cash flow.

Files: Primavera P6 (XER), MS Project XML, PDF

Summary bar chart of the sample river bridge programme, with the critical path in red, monsoon closures shaded and NHAI Schedule-J milestone dates marked
Summary bar chart by pier and span. Red is the critical path; blue bands are the monsoon closures for river-bed works; dashed lines are the Schedule-J dates. Scroll sideways to see the whole chart. Open full size

The project

Bridge
8 spans × 40 m (320 m), two lanes; supports A1, P1–P7, A2
Foundations
76 bored cast-in-situ piles, 1.2 m dia (2,352 m), with an initial test pile and load tests
Substructure
Pile caps, pier shafts in two lifts, pier caps on truss, bearing pedestals
Superstructure
40 precast PSC I-girders from a 3-bed casting yard, crane erection, deck slab, crash barriers
Approaches
250 m each side: RE walls, embankment, GSB, WMM, DBM and BC
Resources in the logic
2 piling rigs in the river and 1 on land; shutter and truss sets moving pier to pier; 1 crane pair; 2 deck shutter sets
Contract dates
Appointed Date 2 Nov 2026; Scheduled Completion Date 1 Nov 2028 (730 days, illustrative)

Results

Planned completion
16 May 2028
Milestone-I (35% of the period)
10% stage payments required, 56% planned
Milestone-II (60%)
35% required, 93% planned; all bridge works started
Milestone-III (85%)
70% required, 100% planned
Cost-loaded S-curve and monthly cash flow of the sample bridge, with the Schedule-J stage-payment requirements marked
Cost-loaded S-curve and monthly cash flow, with the Schedule-J stage-payment tests.

What to notice

  • The monsoon decides this job. Pier P4's piling is cut off on 15 June and resumes in October, which puts P4 on the critical path. Starting the river piles two weeks earlier, or adding a third rig by April, takes it off.
  • The Authority's Engineer's drawing reviews (15 days, up to 30 for a major bridge, under Clause 10.2) sit in the logic in front of the piling, substructure and girders they hold up.
  • Girders are cast once both supports of a span have their first shaft lift, so 40 girders are not stacked in the yard for months.
  • The monthly cash flow comes from the same file and is checked against the Schedule-J stage-payment thresholds, which is what Part III of the programme asks for.

Where each duration comes from

A few rows from the programme. Every activity carries its basis in its notes, so your engineer can check it.

ActivityDurationBasis
Working piles, pier P1 (8 nos)24 days8 piles × 3.0 days per pile per rig
Pile cap, P1 (~108 m³)6 daysDry pile cap cycle, 5–6 days
Pier shaft, one lift5 days4–5 days per lift; 1 day after the pile cap
Pier cap on truss (~80 m³)10 days9–11 days; 3 days after the last shaft lift
Girder casting, one span (5 girders)6 days5 girders ÷ 3 beds × 3 days per bed cycle, plus stressing
Girder erection, one span4 days3–4 days per span with 2 cranes
Deck slab, one span (~129 m³)18 daysAbout 3 weeks per span; 2 shutter sets
Expansion joints (9 nos)25 days9 joints × 5 days ÷ 2 crews, × site factor
AE review of foundation drawings30 daysNHAI EPC Clause 10.2(iv)(c): up to 30 days for a major bridge

MS Project · from a real measured BOQ

B + G + 21 mixed-use tower, Mumbai

A 21-storey redevelopment tower with shoring, rock anchors and a raft, programmed floor by floor from our own measured BOQ, so the S-curve is the BOQ's money.

Files: MS Project XML, Primavera P6 (XER), PDF

Floor-by-floor flowline of the sample tower programme, showing the slab pours, masonry, plaster, flooring and finishing trades rising storey by storey, with the monsoon periods shaded
Floor-by-time flowline: each line is a trade moving up the building; amber blocks are the external plaster drops; blue bands are the monsoon. Scroll sideways to see the whole chart. Open full size

The project

Building
Basement, ground, two commercial floors, two parking podiums, an amenity floor and residential floors to the 21st
Enabling works
253 shore piles of 300 mm, capping beam and waler, three-stage excavation with two rows of rock anchors
Structure
750 mm raft; podium slabs on a 16-working-day cycle; typical slabs on a 12-working-day cycle with 3 formwork sets
Finishes
Floor by floor: masonry, MEP rough-in, plaster, waterproofing and flooring, doors, windows and paint; two gangs per trade
External works
Plaster and paint in drops from the terrace down, kept out of the monsoon
Cost loading
All 249 items of the measured BOQ, ₹25.57 crore excluding GST and owner-supplied lifts, spread floor by floor

Results

Start
2 Nov 2026
Excavation and anchors
Feb–Apr 2027, before the monsoon
Structure topped out
Jun 2028
Handover
17 Feb 2029 (27½ months)
Cost-loaded S-curve and monthly cash flow of the sample tower, from the priced BOQ
Cost-loaded S-curve and monthly cash flow from the priced BOQ.

What to notice

  • The terrace slab is poured days before the June monsoon closure, and top-down external plaster can't start until October. So the monsoon, not the slab cycle, sets the handover date.
  • The structure has about 80 working days of float. A contractor can use it two ways: hire two formwork sets instead of three, or plaster the lower tower floors before the monsoon and finish about six weeks earlier.
  • Masonry starts 12 working days after the slab above is poured, because props under beams in PPC concrete stay 14 days under IS 456 (Amendment 5).
  • Because every BOQ item is spread over the activities that build it, a lender's engineer or a RERA quarterly report can be checked against the same S-curve.

Where each duration comes from

A few rows from the programme. Every activity carries its basis in its notes, so your engineer can check it.

ActivityDurationBasis
Shore piles (253 nos, 2 rigs)32 days253 piles ÷ (2 rigs × 4 piles per rig-day)
Excavation stage 1 (~1,211 m³)12 days1,211 m³ ÷ 120 m³ a day × 1.1 site factor
Typical floor: columns and core walls4 daysAbout 39 m³ of vertical RCC
Typical floor: slab formwork and steel6 days333 m² plate, 3 formwork sets
Floor 10: masonry (55 m³)7 days55 m³ × 0.6 mason-day ÷ 6 masons × 1.1
Floor 10: internal plaster (914 m²)11 days914 m² × 0.08 mason-day ÷ 8 masons × 1.1 (IS 7272)
Floor 10: waterproofing, flooring and dado (412 m²)13 days412 m² × 0.12 tiler-day ÷ 6 × 1.1, plus 3 days for waterproofing
External plaster, floors 10–13 (1,611 m²)17 days1,611 m² × 0.10 ÷ 12 masons × 1.1, plus 2 days for scaffold

Get your programme built the same way

We reply on WhatsApp within working hours with the scope and a fixed price. Nothing starts until you confirm.

Prefer WhatsApp? Send it there
Your BOQ and contract pages *

The BOQ (or the tender BOQ) and the pages that set the milestones, the completion period and the software. Drawings help too: plans and a section for buildings; the GAD and plan-profile for bridges and roads. Not needed for a bid bar chart from the BOQ.

PDF, Excel or DWG, several files allowed, up to 4 MB in total.

Contract details (optional)

We reply on WhatsApp within working hours with the scope and a fixed price. Tender documents stay confidential; NDA on request.

Frequently asked questions

Are these real projects?

The tower is programmed from a real BOQ we measured for a Mumbai redevelopment, with the client, site and address withheld. The bridge is an illustrative NH EPC package, built with the cycle times and logic that bridge contractors use on pile-foundation river bridges. Both were built with the engine and norms we use for paid work.

Can I get the Primavera or MS Project file?

Yes. The PDF extract is free on this page; ask on WhatsApp for the XER or MS Project file and tell us the software version you use.

Why does the bridge finish so long before its contract date?

Its 730-day contract period is illustrative. The sample shows where the float sits: the river piers are held up by the monsoon, so the critical path runs through pier P4, while the casting yard and the approaches have months of float. Your programme uses your contract's dates.

What do the colours mean?

On the bridge chart, red bars are the critical path, blue bands are the monsoon closures for river-bed works, and dashed lines are the NHAI Schedule-J milestone dates. On the tower flowline, each line is a trade moving up the building and the amber blocks are the external plaster drops.