Work breakdown structure construction example (for Indian contractors)
A Work Breakdown Structure (WBS) is one of the fastest ways to bring control to a construction site. Instead of running the project on memory, WhatsApp messages, and a high-level schedule, you break the full scope into clear deliverables and trackable work packages.
In this guide, you will get a practical work breakdown structure construction example for a typical Indian G+4 building, along with best practices to make your WBS usable for planning, subcontractor coordination, and RA billing.
What is a Work Breakdown Structure (WBS) in construction?
A construction WBS is a hierarchical breakdown of the project scope into smaller deliverables, down to work packages that can be assigned, measured, and verified.
It is not the same as your Gantt chart. Your schedule answers when work happens. Your WBS defines what must be delivered. A strong WBS follows the 100% rule: it covers 100% of the scope, and nothing outside the scope.
WBS vs BOQ vs schedule
- WBS: Scope broken into deliverables and work packages (execution structure)
- BOQ: Quantity and payment structure (commercial structure)
- Schedule: Sequence and dates (time structure)
On well-run projects, these three are linked using WBS codes.
Why WBS matters (real trends and numbers)
Construction is getting larger, faster, and more demanding on documentation. IBEF notes that India’s Union Budget 2025–26 increased infrastructure capital investment outlay to Rs. 11.21 lakh crore (3.1% of GDP), which means more work and tighter timelines across the ecosystem.
At the same time, the industry still loses time on avoidable coordination issues:
- McKinsey Global Institute has reported that construction productivity has historically grown at about 1% per year globally.
- The PlanGrid + FMI report Construction Disconnected highlighted that teams spend 14+ hours per week on non-productive activities (searching for information, rework, conflict resolution).
- Recent academic reviews of Indian infrastructure projects (roads/bridges) continue to rank material issues, site challenges, and contractor inefficiencies among the top delay drivers.
A WBS does not replace good supervision, but it creates a shared map of the job so your site engineer, foreman, subcontractors, and office team are working from the same breakdown.
What a good construction WBS looks like
Levels (keep it practical)
Most SMB projects need 3–4 levels:
- Level 1: Project
- Level 2: Major deliverables (substructure, superstructure, finishes, MEP, external works)
- Level 3: Sub-deliverables (slabs, brickwork, plaster, wiring)
- Level 4: Work packages (floor-wise/zone-wise tasks you can track weekly)
Work packages with a clear definition of done
A work package should be measurable. For example:
- Bad: Toilet waterproofing done
- Better: Toilet waterproofing for Flat 2B, 2nd floor, including primer + membrane, 24-hour pond test, and punch list closure
WBS dictionary (simple template)
For critical items, keep a short WBS dictionary entry:
- scope boundaries and drawings/spec reference
- measurement method (sqm, rmt, points, cum)
- responsible person/subcontractor
- quality checks (hold points)
- dependencies (what must be ready before starting)
Code your WBS
Use a consistent code like 1.4.2.5 across daily reports, checklists, and billing backups.
How to create a WBS for an Indian construction project (step-by-step)
1) Start from scope and latest drawings
Collect architectural, structural, and MEP drawings (IFC if possible), specifications, and your BOQ/estimate. If scope is still changing, create a draft WBS and mark open decisions.
2) Decide the breakdown logic (hybrid works best)
Common breakdown styles:
- By phase: pre-construction → substructure → superstructure → finishes → handover
- By trade: civil → electrical → plumbing → fire → HVAC
- By location: wing-wise, floor-wise, flat-wise
For Indian building projects, a hybrid approach works well: phase/trade at Level 2, then floor-wise or flat-wise at Level 3/4 (because repetition is high).
3) Build Level 2 deliverables (8–12 buckets)
Level 2 should match how you manage the job: major subcontract packages, major billing heads, and major milestones.
4) Break each deliverable into Level 3 components
Example: under Superstructure, separate columns, beams/slabs, stair, lift core, terrace.
5) Convert Level 3 items into trackable work packages
A good work package is something your team can complete in a few days to two weeks, such as:
- slab shuttering (3rd floor)
- rebar fixing (3rd floor)
- electrical conduit in Wing A (1st floor)
- plaster in Flat 102
6) Add the items that cause surprises
Indian sites often slip because these were not planned in the breakdown:
- inspections/hold points (plinth, waterproofing pond test, pressure testing)
- temporary works (scaffolding, safety nets, lighting)
- testing and documentation (cube tests, pour cards, checklists)
- procurement lead-time items (lift, windows, tiles, CP fittings, DG/solar)
- monsoon protection and dewatering
7) Map WBS to BOQ and subcontract measurement
If your RA bills are BOQ-based, map WBS items to BOQ lines so your progress reports directly support billing. For item-rate subcontractors, use the same WBS codes in the measurement sheets.
8) Build the schedule from the WBS
Use the WBS as the backbone for your schedule (MS Project/Primavera/Excel). Activities should roll up cleanly to deliverables.
9) Assign ownership and handoffs
For each work package, define:
- executor (subcontractor/gang)
- checker (site engineer)
- approver (project engineer/PMC/client)
10) Freeze a baseline and control changes
Version your WBS (Rev 0, Rev 1). When scope changes, update the WBS and reflect it in schedule and BOQ mapping.
Work breakdown structure construction example: G+4 RCC residential building
Assume a typical Indian apartment building: RCC frame, brick/AAC infill, lift, standard electrical and plumbing, basic compound wall and paving.
Level 1 to Level 3 WBS (deliverables)
- 1.0 G+4 Residential Building Project
- 1.1 Pre-construction & Approvals
- 1.1.1 Survey, benchmarks, grid setting out
- 1.1.2 Soil test and foundation design sign-off
- 1.1.3 Statutory approvals/NOCs as applicable
- 1.2 Mobilization & Temporary Works
- 1.2.1 Site setup (office, storage, labour facilities)
- 1.2.2 Temporary water/power, site lighting
- 1.2.3 Safety barricading, signage, access
- 1.3 Substructure
- 1.3.1 Excavation, PCC
- 1.3.2 Footings and pedestals (rebar + concreting)
- 1.3.3 Plinth beam, backfilling, compaction
- 1.3.4 Termite treatment and plinth protection
- 1.4 Superstructure (RCC)
- 1.4.1 Columns and shear walls (floor-wise)
- 1.4.2 Beams and slabs (floor-wise)
- 1.4.3 Staircase and lift core (if in scope)
- 1.4.4 Terrace slab, parapet, mumty
- 1.5 Masonry & Plaster
- 1.5.1 External and internal masonry (floor-wise)
- 1.5.2 Lintels/sills/chajjas as required
- 1.5.3 Internal plaster (flat-wise)
- 1.5.4 External plaster/finish
- 1.6 MEP Rough-in and Testing
- 1.6.1 Electrical conduits/boxes/DB locations
- 1.6.2 Plumbing lines and pressure tests
- 1.6.3 Drainage/vent lines and slope checks
- 1.6.4 Earthing and lightning protection
- 1.7 Waterproofing (high-risk scope)
- 1.7.1 Terrace waterproofing + pond test
- 1.7.2 Toilet and balcony waterproofing + pond test
- 1.8 Finishes & Fixtures
- 1.8.1 Flooring and skirting
- 1.8.2 Doors/windows/grills and hardware
- 1.8.3 Putty, primer, painting
- 1.8.4 Sanitary and electrical fixtures
- 1.9 External Works & Handover
- 1.9.1 UG sump/overhead tank connections (if applicable)
- 1.9.2 Compound wall, gate, paving
- 1.9.3 Testing, snag closure, documentation, handover
- 1.1 Pre-construction & Approvals
Expanding one item into Level 4 work packages (floor-wise example)
Expand 1.4.2 Beams and slabs (floor-wise) for one typical floor:
- 1.4.2.1 Shuttering/centering for slab and beams (2nd floor)
- 1.4.2.2 Rebar fixing as per BBS (2nd floor)
- 1.4.2.3 MEP sleeves/openings verification (2nd floor)
- 1.4.2.4 Pre-pour checklist and inspection sign-off (2nd floor)
- 1.4.2.5 Concrete pour + cube sampling + finishing (2nd floor)
- 1.4.2.6 De-shuttering, curing, and line/level checks (2nd floor)
Mini WBS dictionary entry (copy-paste)
WBS Code: 1.4.2.5
- Work package: 2nd floor slab concrete pour
- Inputs: Approved shuttering and rebar, MEP sleeves cleared, pour card ready
- Measurement: cum of concrete placed (with grade)
- Quality checks: slump, cubes, level tolerance, curing start time
- Done when: pour report submitted, cubes logged, curing initiated, surface accepted
How to use your WBS on site (daily, weekly, billing)
- Weekly lookahead: pick the next 10–20 work packages, confirm drawings, materials, manpower, and inspections.
- Daily execution: assign packages to subcontractors/gangs, and capture progress with photos and quantities.
- Billing support: because WBS is mapped to BOQ, you can quickly build RA bill backups from verified quantities.
Many contractors start with Excel, but execution becomes hard when updates are scattered. Tools like SiteSetu help keep your WBS-linked tasks, photos, checklists, and documents in one place so your team always works on the latest information without adding paperwork.
Common WBS mistakes (quick fixes)
- Too detailed on day one → start Level 2–3, expand only critical packages.
- No acceptance criteria → define done for waterproofing, MEP tests, and handover.
- Not aligned to how work happens → break floor-wise/flat-wise where repetition exists.
- No change control → revise the WBS when scope changes, not just the schedule.
FAQs
Is WBS only for big projects?
No. Even small residential jobs benefit because it prevents missed scope (tests, inspections, commissioning).
Should WBS match BOQ exactly?
Not exactly, but it should be mapped to BOQ so progress and billing stay consistent.
How many WBS levels are enough?
For most Indian SMB projects, 3–4 levels is practical.
Final takeaway
If you want fewer surprises, start with a clear WBS and run your site routines from it. Use the construction example above as a base, adapt it to your project type, and keep improving it as you learn from each job.
Trusted External References
Useful official portals for construction policy, compliance, and market updates.
Tags: